List Your Equipment For Free  /  Seller Login

Racing to Beat the Next Hurricane Season

Mon November 30, 2020 - Southeast Edition #25
Lori Lovely – CEG Correspondent


The total awarded to date for the Louisiana Floodgate is $55,377,912, which is well below budget.
The total awarded to date for the Louisiana Floodgate is $55,377,912, which is well below budget.
The total awarded to date for the Louisiana Floodgate is $55,377,912, which is well below budget. In the Paver Canal, crews are building up the height, using what they dredge out of the river for the pilings. The “jackets” for the pilings that 
go into the water are delivered by barge. You can get an idea how big they are by looking at the 
cranes next to them. The pilings and the paver canal. Riprap scour protection will be provided within the channel as needed. Protection fendering and dolphins will be provided in the Bayou Chene channel. Work is under way to construct a permanent floodgate on Bayou Chene near Morgan City, La., that will provide backwater flood protection for six parishes in the path of Mississippi and Atchafalaya river overflows that result from high water events. The floodgate cutoff wall will be a steel sheet pile wall with a steel cap to receive the floodgate seals. The sill elevation will be -24.0 NAVD88. The floodgate features a pumping system consisting of electric submersible pumps and an electric/hydraulic winching system with electrical power from a generator. A levee district summary predicted a completion date sometime in mid-2022, but CPRA is aiming for late next year to have the floodgate and remaining components of the project, including road improvements, armored earthen levee and a weir structure complete and operational. The floodgate itself will be a steel barge gate with a pivot pile and winch operation. The elevation of the barge gate will be 10.0 NAVD88.

Work is under way to construct a permanent floodgate on Bayou Chene near Morgan City, La., that will provide backwater flood protection for six parishes in the path of Mississippi and Atchafalaya river overflows that result from high water events.

Bayou Chene, approximately 9 mi. southeast of Morgan City and 50 mi. south of Baton Rouge, was first settled in the 1830s. During high-water events on the Atchafalaya River, Bayou Chene has been a major conduit for backwater flooding in the parishes of St. Mary, Terrebonne, Lafourche, St. Martin, Assumption and Iberville. High water flowing down the Atchafalaya past Morgan City will turn and head northwest up Bayou Chene into the Lake Palourde and Lake Verret watersheds, causing flooding across that region.

The area has experienced a number of floods since the early 20th century, but three major floods in the last 10 years led to the decision to find a permanent solution.

"Backwater flooding in St. Mary and neighboring parishes has increasingly been a problem over the past decade as the Mississippi River and in turn, the Atchafalaya, has reached flood stage," said Gov. John Bel Edwards.

In May 2011, the St. Mary Levee District experienced unprecedented high-water elevation predictions for St. Mary, Terrebonne, Lafourche, St. Martin, Assumption and Iberville parishes. In preparation, SMLD built a temporary flood protection structure consisting of a barge floodgate, sheet pile floodwalls, rip rap and Hesco baskets. According to Ignacio Harrouch, chief, operations division of the Coastal Protection and Restoration Authority, this structure withheld an additional 3 ft. of water from the parishes in jeopardy.

Five years later, another high-water event in the Atchafalaya River threatened the surrounding six-parish area, so SMLD contracted an engineering firm to design an emergency structure to prevent backwater flooding.

"The structure was designed, bid and constructed in 15 days, utilizing existing wing walls from a previous flood fight," Harrouch reported. The structure was later removed due to a water differential greater than 1 ft. between the protected and unprotected sides.

According to KATC News, St. Mary Parish President David Hanagriff said, "In 2016, it took 15 days to design, bid, build and install the temporary barge. It did the job, but it wasn't cheap and it had to be removed after the flood threat passed because it was blocking navigation. Having a permanent structure we can open and close is a better, smarter solution."

As long ago as 1973, the emergency method of flood control in times of high water in the Atchafalaya consisted of temporarily sinking a barge in the Bayou Chene channel. Once flooding subsided, the temporary barge floodgate was removed to allow for normal drainage and boat traffic.

However, the deployment and removal of the temporary barge as a flood control measure is costly. St. Mary levee officials said the 2016 closure cost $7 million. In 2018, the emergency structure cost $5.2 million. Edwards describes sinking barges as a "costly and short-term approach" and expects this permanent structure to provide a reliable, long-term solution.

In addition, Harrouch expressed concerns that failure to come up with an effective plan could result in loss of reimbursement from FEMA for future floods.

Devising a Plan

As early as 2011, CPRA began considering a project for a more permanent solution to protect the area from the swamps southeast of the bayou to Morgan City to the northwest. In addition to $5 million the agency put up for engineering and design, it acquired an additional $75 million in of Gulf of Mexico Energy Security Act funds for construction.

But before that happened, another flood took place.

"In May 2019, APTIM was hired to design the emergency structure yet again to prevent backwater flooding while the permanent structure was being designed," Harrouch said. This project was completed in 11 days from design to construction. It was the third time in less than 10 years that a barge was deployed to assist with flood control, underscoring the need for a permanent solution.

That solution will feature steel braced floodwalls that extend from both the north and south banks of Bayou Chene to the flood gate receiving structure in the channel. The floodgate will consist of an automated 403-ft. clear opening barge gate that can swing into place and be ballasted, providing 10 ft. of flood protection against high-river events. Harrouch pointed out that the 400-ft. floating steel gate will be the largest floodgate in Louisiana. When closed, using a winch and tugboats, it will act as a dam, protecting more than 100,000 residents in a six-parish region with the push of a button.

The project also will include protection fendering systems in the Bayou Chene channel and riprap scour protection. The existing parish road (Avoca Road) and an existing levee berm from Avoca Road to the north side of the Bayou Chene structure (totaling approximately 7 mi.) will be raised to an 8-ft. elevation. On the south side, an 8-ft.-elevation earthen levee with geotextile fabric will connect the structure to the Tabor Canal levee, which also will be elevated to 8 ft., utilizing the existing berm and geotextile fabric.

Project Design

Design, engineering and construction management was led by several Louisiana-based engineering firms: APTIM Environmental & Infrastructure led the project, with support from T. Baker Smith, Miller Engineers and Associates, Eustis Engineering and FTN.

APTIM, with eleven offices in Louisiana, designed the 10,000-ft.-long, 26-ft.-high storm surge barrier across Lake Borgne as part of the Greater New Orleans Hurricane Storm Damage Risk Reduction System.

Overseen by the Coastal Protection and Restoration Authority and St. Mary Parish Levee District, the project is being divided into six phases:

  • Phase IA: Clearing and Grubbing Tabor Canal
  • Phase IB: Dredging
  • Phase 2: Floodwall and Receiving Structure
  • Phase 3: Floodgate and Pivot Pile
  • Phase 4A: Avoca Road Retrofit
  • Phase 4B: Tabor Canal and Weir

Phase IA has been completed. Phase 1B is expected to wrap up in November, with material being placed to raise the elevation of Tabor Canal. An E-Crane owned by Patriot Construction & Industrial was used to place dredged material along Tabor Canal.

Phases 2 and 3 are under way and are expected to be completed in August 2021. Phase 4A was recently awarded and began in October, with completion anticipated in June 2021.

Phase 4B will be let to bid in March 2021. According to Harrouch, Louisiana state law requires all funding to be in place prior to bidding, but CPRA has not yet received all the money.

Construction firms awarded to each phase:

  • Phase IA: Patriot Construction $358,300.00
  • Phase IB: Patriot Construction $3,237,927.00
  • Phase 2: Sealevel Construction $23,695,414.50
  • Phase 3: Sealevel Construction (including Bollinger sub-contractor) $22,737,642.00
  • Phase 4A: Rigid Construction $5,348,629.00
  • Phase 4B: TBD

The total awarded to date is $55,377,912, which Harrouch points out is well below budget. One assist to budget savings comes from sheet pile purchased for the 2011 and 2016 floods that was left in place to accommodate another temporary flood protection structure in anticipation of future flooding and is now being utilized and incorporated into the project as owner-supplied materials.

Project Checklist

The project includes raising the Avoca Road Levee, an existing parish road, to approximately elevation 8.0 NAVDD88. This levee will extend approximately 7 mi. from the Bayou Beouf locks towards the floodgate. Crews will tie in the existing Corps Disposal Berm Levee from Avoca Rd. to the north side of the Bayou Chene and elevate it to a minimum elevation 8.0 NAVD88.

The Bayou Chene Flood Control Structure will consist of steel-braced floodwalls to elevation 10.0 NAVD88 and will extend from the north and south sides of the floodgate receiving structure, which will be a jacket-type structure to elevation 10.0 NAVD88. The floodgate cutoff wall will be a steel sheet pile wall with a steel cap to receive the floodgate seals. The sill elevation will be -24.0 NAVD88.

The floodgate itself will be a steel barge gate with a pivot pile and winch operation. The elevation of the barge gate will be 10.0 NAVD88. It will feature a pumping system consisting of electric submersible pumps and an electric/hydraulic winching system with electrical power from a generator.

Riprap scour protection will be provided within the channel as needed. Protection fendering and dolphins will be provided in the Bayou Chene channel.

The existing temporary Bayou Chene closure structure will be removed. Materials from it will be utilized in the proposed structure as much as possible.

Other aspects of the project include the Tabor Canal Levee, which will extend from the south structure tie-in to the Tabor Canal Levee and the Tabor Canal Levee, which will extend from the confluence of Tabor Canal and Bayou Chene to the South end of Tabor Canal.

The Tabor Canal levee crosses two pipelines: the Enterprise Pipeline Crossing and the Tennessee Pipeline Crossing, both of which are anticipated to be earthen levees.

The Tabor Canal weir/gate closure will be constructed to elevation 8.0 NAVD88.

Challenges

"Permitting was the largest challenge and delay to date," Harrouch said. "The project was redesigned from a 250-ft. clear opening in the 15 percent design phase to a 403-ft. clear opening in the later design phases, and sluice gates were added to the floodwall to accommodate permitting agencies comments."

Traditional designs are submitted with 30-60-95 percent phases, but to expedite the work in the hopes of completing the project before the next hurricane season, this project was designed with 50-100 percent phases, Harrouch explained. "We're working hard to do things that will expedite the work."

An emergency operation plan was required in case a storm threat shuts down work. Nevertheless, while a levee district summary predicted a completion date sometime in mid-2022, he said CPRA is aiming for late next year to have the floodgate and remaining components of the project, including road improvements, armored earthen levee and a weir structure complete and operational.

But there are challenges beyond the weather. Access is one of them. Equipment and materials such as the jackets — which are used to place the piles — must be transported to the site by barge. Massive cranes are situated on barges to drive the piles and sheet wall. Because they were unable to use coffer dams, crews must jet the pile down with air and then drive them in this "in the wet" construction method. Harrouch reported no issues with the process, citing the heavy clay soil.

The floodgate is being fabricated at Bollinger Shipyard in Amelia, La., and will be towed by tugboats to the site, after which Louisiana-based Sealevel Construction Inc. will install the structure.

Knowing that "this project will alleviate backwater flooding in a six-parish area," Harrouch considers it "extremely significant" and said CPRA has gotten creative on the budget, design and implementation. CEG


Lori Lovely

Lori Lovely is an award-winning journalist, editor and author of the children's book Isadora's Dance. She has worked for newspapers, magazines and niche publications, covering a wide-ranging list of topics that includes motor sports, construction, MSW, energy, environmental issues, water, animal rights and issues, history, Native American issues and people, real estate and home decor, farming and more. Her degrees in History taught this dedicated professional to research thoroughly and ask detailed questions in order to winnow interesting facts that convey the essence of the story. As a seasoned writer and compassionate storyteller, she accurately portrays the subject in a manner that entrances the reader.

When she's not working on assignment, Lori is tending to her historic Indiana farm, where she raises alpacas. An inveterate animal lover, this vegetarian enjoys spending time with her animals and working in her garden.


Read more from Lori Lovely here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA