List Your Equipment For Free  /  Seller Login

Rehabilitation of Eight Bridges in Chester Nears End

Thu August 27, 2020 - Northeast Edition #18
Brenda Ruggiero – CEG Correspondent


A PennDOT project to rehabilitate eight bridges over Interstate 95 and CSX Railroad in the city of Chester in Delaware County, Pa., is nearing completion.
A PennDOT project to rehabilitate eight bridges over Interstate 95 and CSX Railroad in the city of Chester in Delaware County, Pa., is nearing completion.
A PennDOT project to rehabilitate eight bridges over Interstate 95 and CSX Railroad in the city of Chester in Delaware County, Pa., is nearing completion. Work began in the fall of 2016 and is scheduled to be finished by late summer 2020. The full dollar amount is $30.3 million for construction, with 100 percent coming from the state. The contract was awarded to South State Inc. of Bridgeton, N.J. Brad E. Rudolph of PennDOT’s Engineering District 6 said South State Inc. will rehabilitate and improve the multi-span, steel girder bridges on Potter Street, Madison Street, Upland Street, Melrose Avenue, Chestnut Street, Edgmont Avenue and the Walnut Street and Crosby Street pedestrian structures. The main challenge is extensive coordination on the project with other transportation agencies and community stakeholders such as Amtrak, CSX, Chester Water Authority, PECO Electric and Gas, Verizon, Widener University and city of Chester.

A PennDOT project to rehabilitate eight bridges over Interstate 95 and CSX Railroad in the city of Chester in Delaware County, Pa., is nearing completion.

Work began in the fall of 2016 and is scheduled to be finished by late summer 2020.

The full dollar amount is $30.3 million for construction, with 100 percent coming from the state. The contract was awarded to South State Inc. of Bridgeton, N.J.

According to Brad E. Rudolph, deputy communications director 2 for PennDOT's Engineering District 6, the contractor will rehabilitate and improve the multi-span, steel girder bridges on Potter Street, Madison Street, Upland Street, Melrose Avenue, Chestnut Street, Edgmont Avenue and the Walnut Street and Crosby Street pedestrian structures.

The contract also calls for the improvement of the I-95 south exit ramp at Chestnut Street.

"Crews will place a new concrete overlay on the bridges; repair piers and support abutments; replace fencing on the bridge parapets; repair curbs and sidewalks; install new expansion joints; paint structural steel; reset bridge bearings; clean bridge drainage systems; repair existing lights; and perform other miscellaneous repairs," Rudolph said.

In addition to the bridge and ramp improvements, PennDOT's contractor will repair Chestnut Street and Morton Avenue from 12th Street to 4th Street.

"The plan is to reconstruct curbs and sidewalks; mill and resurface the streets; install a new traffic signal at Chestnut Street and Morton Avenue; and upgrade the traffic signal at Morton Avenue and 7th Street," Rudolph said. "The contractor will reconstruct Morton Avenue from 7th Street to 4th Street to lower the road under the Amtrak overpass to increase vertical clearance from 12 feet 9 inches to 13 feet 9 inches."

According to Rudolph, PennDOT owns the Edgmont Avenue and Madison Avenue bridges, and the city of Chester owns the remaining six structures.

He reported that the main challenge is "extensive coordination on the project with other transportation agencies and community stakeholders such as Amtrak, CSX, Chester Water Authority, PECO Electric and Gas, Verizon, Widener University and city of Chester."

Another challenge noted was that concrete repairs and epoxy crack injection repairs to concrete substructure were performed mostly at night.

Crews also had to deal with parked trains on CSX tracks and the requirement to maintain protection of CSX tracks.

Rudolph reported that the most unique aspect of the job involves lowering Morton Avenue to increase clearance under the Amtrak bridge along Morton Avenue to the intersection of Route 291.

"The clearance posted at the start of the project was 12 feet, 9 inches and the current clearance is posted at 13 feet, 11 inches," he said. "The department directed the use of concrete base course under the Amtrak bridge to ensure long life to the asphalt roadway."

He noted that the Morton Avenue segment of the project called for increased drainage, utility upgrades, signal and safety improvements and installation of over 60 ADA ramps along the Morton Avenue corridor in conjunction with the improvements to eight bridges — two state-owned and six bridges owned by the city of Chester, two of which are pedestrian bridges.

"The contractor had many utility challenges to circumvent while extensively upgrading the storm sewer system," Rudolph said. "This required the contractor to have many crews of different expertise to be working on the project at one time. The project had three I-95 ramps: two on-ramps, one NB, one SB, and one off-ramp SB I-95."

The ramp from I-95 SB was a major access to Widener University for student move-in days in August.

A Safe Span scaffolding system was installed for M Painting crews on as many bridges as possible where clearance was not a concern.

Randolph reported that the project included 77 tons of steel for repairing the beams, the replacement of over 200 bearings at the bridges, latex overlays at Madison, Upland and Chestnut totaling 24,520 sq. ft. and concrete decks replaced at Potter and Melrose totaling 22,850 sq. ft.

M Painting was subcontracted to blast and paint bridge beams, which was approximately 25 percent of the original contract bid. A Safe Span scaffolding system was installed at numerous bridges with ample overhead clearances.

Cornell Steel completed repairs to add service life to bridges originally built in the 1960s. CJ Drilling installed caisson for the new sign structure as the current bridge design no longer utilizes structure mounted signs. Apex Fence installed fence for increased safety to the travelling public on I-95 below. Carr & Duff upgraded the signals at 7th and Morton and signalized the intersection at 10th and Morton and Chestnut.

The equipment list, all owned by South State Inc., includes a GOMACO concrete deck finishing machine, a crane to hang the Exit 7 sign and various excavators, dozers and earthmoving machinery.

A trailer-mounted platform boom truck was used for reaching workers under the bridge. This was required due to access restrictions over CSX tracks. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA