List Your Equipment For Free  /  Seller Login

Repairs Under Way on Longest Suspension Bridge in New England

Fri September 01, 2017 - Northeast Edition #18
Lori Tobias


Work is well under way on a project to repair the deck of Rhode Island’s Newport/Pell Bridge — at 11,247 ft. long, it is the longest suspension bridge in New England.
Work is well under way on a project to repair the deck of Rhode Island’s Newport/Pell Bridge — at 11,247 ft. long, it is the longest suspension bridge in New England.
Work is well under way on a project to repair the deck of Rhode Island’s Newport/Pell Bridge — at 11,247 ft. long, it is the longest suspension bridge in New England. In the first sequence, crews with the Aetna Bridge Company, based in Warwick, R.I, closed two lanes of the four-lane bridge, limiting traffic to one lane in each direction. Traffic delays were about a half an hour. This first phase is divided into three sequences. The first extended from May 15 through June 30 and involved the hydro-demolition of the top 3 to 4 in. of the 8-in. deep concrete deck. “This is a major undertaking replacing the deck of this bridge,” said Jim Malachowski, spokesman of the RDW Group, the Providence-based public relations firm representing the Rhode Island Turnpike and Bridge Authority. The bridge was built in 1969 with a roadway height of 215 ft. above the water and towers reaching 400 ft. The second sequence is under way now and involves work beneath the bridge. That allows traffic to flow in all four lanes during Rhode Island’s busy tourist season.

Work is well under way on a project to repair the deck of Rhode Island's Newport/Pell Bridge — at 11,247 ft. long, it is the longest suspension bridge in New England.

“This is a major undertaking replacing the deck of this bridge,” said Jim Malachowski, spokesman of the RDW Group, the Providence-based public relations firm representing the Rhode Island Turnpike and Bridge Authority.

“It's quite a project. The bridge has five different architectural/engineering design components. The bridge deck had an expected life span of 25 to 30 years. The Rhode Island Turnpike and Bridge Authority has paid a great deal of attention to extend the life of the deck, which has been great. It's paid dividends; the bridge is now 48 years old.

“This is just the first phase of a multi-phase, multi-year project. The first phase is expected to cost about $8.1 million. They have a 10-year capital plan. They figure all of this replacement is going to take six to seven years.”

This first phase is divided into three sequences. The first extended from May 15 through June 30 and involved the hydro-demolition of the top 3 to 4 in. of the 8-in. deep concrete deck. Workers also poured new concrete

“They got down to rebar and they did this curb to curb,” said Malachowski. “There were no problems with the concrete deeper than that. So, this really helped with the cost not to replace the entire deck.

“They didn't start until May because there is a chemical reaction for concrete to harden and cure. If you don't get the right temperature, it won't cure correctly and that would not be good for the bridge. When you come out of the winter, the water takes a while to warm up. You can cover the concrete with blankets and heaters, but they felt it was better to wait to start until May.”

In the first sequence, crews with the Aetna Bridge Company, based in Warwick, R.I, closed two lanes of the four-lane bridge, limiting traffic to one lane in each direction. Traffic delays were about a half an hour.

The second sequence is under way now and involves work beneath the bridge. That allows traffic to flow in all four lanes during Rhode Island's busy tourist season.

“In addition to the deck repair, they also are replacing the bearings below,” Malachowski said. “This is pretty significant. The bridge deck sits on concrete beams and the beams have bearings between them and the pier cap. The concrete beams are all being replaced so they literally have to slightly jack up the parts of the bridge to get the old bearings out and the new bearings in. You have two columns that come up out of the water, then the pier caps, the bearings, concrete beams and then the bridge deck.”

Beginning in mid-September, the crews will begin the third sequence, demolishing and replacing another section of concrete. That work is expected to last until December.

The bridge was built in 1969 with a roadway height of 215 ft. above the water and towers reaching 400 ft.

“When it was built, there was a Navy base in Newport so part of the reason for the heightened magnitude of the bridge was so that navy vessels could pass. The Navy base has since closed. But Newport still has the U.S. Navy War College, which is quite a place. Anyone who wants a career as an officer with the Navy wants that on their resume. We still have navy vessels visiting so it's still necessary to have a bridge of that magnitude.”

Workers will return in coming years to do additional work, but the schedule has not been announced nor have they discussed how they will approach future projects.

“They are really going to step back and consider the lessons learned from this first phase,” Malachowski said. “There may be other sections of the bridge that they'll do differently. There may be other sections that don't have the bearings. When they get to the suspension portion, that will be handled differently. They will figure all that out as they move along.”

Here is a project description from the Rhode Island Turnpike and Bridge Authority:

The Newport Pell Bridge Deck Replacement Project consists of work performed on the Newport/Pell Bridge within Spans 22E to the East Abutment (from the Newport shoreline out 2,000 feet onto the bridge roadway). The work to be performed includes the following as outlined below:

• Partial depth hydro-demolition and replacement of the concrete roadway deck from curb to curb;

• full depth demolition and replacement of reinforced concrete joint headers and installation of new joint seals at some piers;

• installation of UHPC link slabs at some piers;

• removal of existing steel bearings and replacement with new elastomeric bearings at all piers;

• repairs to the reinforced concrete safety walks/curbs;

• steel bridge railing modifications/repairs;

• concrete repairs to the pre-stressed concrete superstructure, reinforced concrete pier caps and reinforced concrete piers; and

• other miscellaneous repairs/work items

CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA