List Your Equipment For Free  /  Seller Login

RK Hall Relies on Cat Equipment for U.S. 82 Job

Wed October 21, 2020 - West Edition #22
Irwin Rapoport – CEG Correspondent


 RK?Hall serves as the general contractor covering approximately 17.8 mi. of construction along U.S. 82 that includes expanding and widening the highway in Red River County.

    Widening operations started with crews milling the shoulder, followed by making necessary cuts and fills in the subgrade.

RK Hall LLC started work on the Texas Department of Transportation's (TxDOT) $14.2 million project to expand and improve U.S. 82 in Red River County in September 2019 and despite rains which had impacted the construction last winter, the general contractor is hopeful to meet the anticipated delivery date of September 2021.

The construction zone along U.S. 82 from FM 1159, just east of Clarksville, eastward to the Red River-Bowie County line, covers approximately 17.8 mi.

Crews are widening the existing pavement between the Kickapoo Creek bridge and FM 1699, approximately 4.5 mi., to install passing lanes; extend existing cross drainage structures; improve the bridge rail and metal-beam guard fence; install safety end treatments on culverts; and overlay a new pavement surface on the roadway.

RK Hall and its crews are rehabilitating portions of the shoulders, approximately 9 ft. of the existing shoulder and 4.5 mi. where the passing lanes are overlapping. Crews already have completed the westbound section of the widening and the extension of the cross culverts in that area, as well the grading of the ditches to acquire better drainage for TxDOT's right-of-way. All 17.8 mi. will receive a hot mix overlay towards the end of the project.

"We are in the middle of working on the eastbound section," said Zak Moore, RK Hall's project manager, who noted that the current operations are within a 2-to-3 mi. area. "We did a lot of tree removal at the beginning to make sure no trees were going to compete with the new road that we're building. That was actually quite a large change order for this job."

Project Challenges

Discrepancies in the plans created a challenge.

"Once we milled up some of the road, we found a concrete slab," said Moore. "When this road was originally built, it had a concrete slab under it. We had a couple of problems with that due to the slab extending into where we were rehabilitating the shoulder, but this issue was handled. We have had some utility issues, which we are still fighting in some areas, but most of these issues were headed off early in the project. They were going to be a problem once we got to the eastbound side of the roadway, so we had the utility company go ahead and relocate these conflicting utilities."

Another major challenge was the subgrade on the westbound widening portion of U.S. 82.

"It was unexpected," said Moore. "We needed a change order to cement treat the subgrade on that side and we will be doing the same on the eastbound side. The soil was trapping a lot of water and as we would run equipment across it, it would start pumping water to the top. By cement treating the subgrade before we built the road, it allowed us to bridge over the areas holding water. Ultimately, we will be building a better road for TxDOT. The shoulders and edges of the road are going to hold up much better than they would have had we went ahead and built our road on top of those waterbed areas."

The road widening operations started with crews milling the shoulder, followed by making necessary cuts and fills in the subgrade.

"We're rehabilitating nine feet of existing shoulder where we are adding the passing lanes," said Moore, who noted that this was where the cement treatment paid off. "After milling and rehabilitating the nine feet, we added six feet of subgrade to the roadway and placed our base to build the road even more, so we could get back to elevation that we needed to be at with the appropriate materials. We cement treated this flex base, added a prime coat and paved directly on top of the prime coat with four inches of Type B hot mix."

Equipment

Critical pieces of equipment for the subgrade and flex base widening have included a Bomag sheep's foot roller; Ferguson pneumatic rollers; Cat motor graders, roadway mixers and reclaimers; Cat front end loaders; Cat 316, 336 and 345 excavators; Cat D4 and D5 dozers; water trucks for the cement treated materials; crash trucks for worker protection; and haul trucks for materials.

"They don't have any steel wheels out here for the dirt work portion of the widening even though we do utilize steel wheels for our paving operations," said Moore, "We have quite a lot of equipment out here on a daily basis."

Extending existing cross drainage structures were among the first construction activities before tearing into the subgrade.

"We had to get the culvert extensions done, so we could backfill on top of them," said Moore. "These culvert extensions are key in carrying the water away from the road. The culvert extensions were one of the activities that were the hardest to work around with all the rain. Obviously, some of the bigger culverts would have a lot of water running through them making it impossible to extend these culverts. We were able to combat this in a few locations by utilizing water pumps, but some areas had too much water.

"Another big issue we had to deal with on this project, which I am sure nearly any other construction company can relate to, is the lack of skilled labor in the construction industry. For example, my concrete subcontractor relies heavily on work visa programs to bring skilled crews from Mexico to work with him during the busy portion of the year. However, he was having issues getting these crews brought in due to the onset of COVID-19. Unfortunately, there is not an abundance of skilled concrete crews that are not already working for other companies in the U.S. On top of this, not many young people are going into a trade once they leave high school. A lot of them are going to college to pursue management or business degrees. You could definitely see the effects of this issue throughout this project."

"The majority of the equipment out here is from the subcontractors," said Moore. "We currently have one sub performing the dirt work, DL Lennon, and another for the culvert extensions, JM Yanez, who has two excavators here — a Cat 336 and a Cat 316. Repair and maintenance efforts are minimal for the equipment on this job. The contractors deal with the usual fueling, oil changes and greasing, but the majority of the time the maintenance is fairly minimal. The only three ‘major' instances I can think of were when a turbo on a sheep's foot roller went out, injectors had to be replaced on a Cat 345 excavator and an idler on a dozer had to be replaced. Other than those few issues, the equipment has held up very well."

DL Lennon has an on-site mechanic to handle all their day to day issues with their equipment. If he does not have the necessary tools, someone from their shop will come to fix the equipment.

In regards to RK Hall's equipment, it rents HAMM and Cat pneumatic and steel wheel rollers, and water trucks from dealerships such as Holt CAT, Riggs CAT and United Rentals. RK Hall owns its own paving equipment, which is supplied by Roadtec (Astec) such as its RP – 190e pavers and its shuttle buggies (MTV), which are used for transferring hot mix to the paver. RK Hall also utilizes Bearcat distributor trucks to spray the tack out in front of the paving operations.

"We rented a 2,000 gallon water truck from United Rentals," said Moore. "Our rollers, rented from Riggs and Holt CAT, are a mix of HAMM and Cat models. These dealerships are very responsive in regards to making sure our equipment is properly taken care of."

Close to 20,000 cu. yds. of material will be excavated on this project. In terms of materials being used, there is approximately 13,500 cu. yds. of embankment, 18,000 tons of flex base, and approximately 80,000 tons of hot mix bid to be laid.

Timeline

Paving operations are expected to start in February and continue into the end of April.

"We will begin with the four inches of Type B hot mix on the new eastbound portion of roadway, followed by performing our surface pavement operations throughout the entire 18 miles of the project," said Moore. "We will be working to pave all lanes at one time through the entire length of the project."

Improvement for the bridge rail and metal-beam guard fence will be done after the overlay, when the final roadway elevations will be set.

"TxDOT's specifications require a specific distance between the top of the pavement to the center of the guardrail, so we are having to wait until we lay our final surface to set the MBGF," said Moore.

The installing of safety end treatments on culverts refers to the reinforced concrete pipe in general.

"We use reinforced concrete top [RCP] to extend the existing RCP culverts on the project," said Moore. "Whenever we install safety end treatments, we put the new pipe up to the existing pipe and pour a concrete collar between the two followed by the installation of the SET to the RCP using strips of Ramnek to seal the pipes together." CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA