'Salt &Pepper' Bridge Linking Boston, Cambridge Receives $255M Makeover

The bridge is a crucial link between the two cities and is an important regional connection.

Wed October 19, 2016 - Northeast Edition #21
Irwin Rapoport


White-Skanska-Consigli photo.
MassDOT anticipates that crews will complete the $255 million Longfellow Bridge rehabilitation in June 2018.
White-Skanska-Consigli photo. MassDOT anticipates that crews will complete the $255 million Longfellow Bridge rehabilitation in June 2018.
White-Skanska-Consigli photo.
MassDOT anticipates that crews will complete the $255 million Longfellow Bridge rehabilitation in June 2018. White-Skanska-Consigli photo.
The historical status of the bridge requires that certain portions of the work are refurbished accurately, including spans 1, 2, and 11 that go over dry land. The use of rivets is required for these portions.
 White-Skanska-Consigli photo.
The bridge is a crucial link between the two cities and is an important regional connection. 
 White-Skanska-Consigli photo.
The project began in March 2013 and is being funded by the Commonwealth of Massachusetts and the Federal Highway Administration.
 White-Skanska-Consigli photo.
A new lighting system is being installed and areas along the riverbank disturbed by the construction will be fully restored.
 White-Skanska-Consigli photo.
The project also includes the replacement of the adjacent Frances Appleton pedestrian bridge by widening sidewalks and adding bike lanes. 
 White-Skanska-Consigli photo.
The bridge was extended in 1956 and rehabilitated in 1959. 
 White-Skanska-Consigli photo.
The bridge’s substructure is built of granite block masonry and consists of ten hollow piers and two hollow abutments. 
 White-Skanska-Consigli photo.
The project will restore the historic bridge, built in 1908, including rebuilding its iconic “salt and pepper” towers.

MassDOT anticipates that crews from White-Skanska-Consigli Joint-Venture (WSC) will complete the $255 million Longfellow Bridge rehabilitation between Cambridge and Boston in June 2018.

The project will restore the historic bridge, built in 1908, including rebuilding its iconic “salt and pepper” towers. The bridge is a crucial link between the two cities and is an important regional connection.

The project began in March 2013 and is being funded by the Commonwealth of Massachusetts and the Federal Highway Administration.

The bridge is 2,135 ft. (650.7 m) long and has a deck width of 105 ft. (32 m). The existing structure has two vehicle lanes in each direction, and accommodates 28,000 cars and trucks daily, as well as cyclists and pedestrians. The Massachusetts Bay Transportation Authority's Red Line also uses the bridge.

When completed, the bridge will have two inbound to Boston vehicular travel lanes, one outbound to Cambridge lane, and the two rebuilt MBTA Red Line tracks.

The project also includes the replacement of the adjacent Frances Appleton pedestrian bridge by widening sidewalks and adding bike lanes.

A new lighting system is being installed and areas along the riverbank disturbed by the construction will be fully restored.

The bridge, which has eleven original open-spandrel steel arch spans, plus two steel girder approach spans at the Cambridge end, was extended in 1956 and rehabilitated in 1959. The cross-section provided an upstream 6-ft. (1.8 m) sidewalk and a 33-ft. (10 m) wide roadway while the downstream side consisted of a 10-ft. (3 m) sidewalk and 29-ft. (8.8 m) wide roadway.

The bridge's substructure is built of granite block masonry and consists of ten hollow piers and two hollow abutments. The two central piers carry the neoclassically-inspired dressed granite towers.

Boston area drivers are used to major construction projects affecting traffic. WSC is required to maintain emergency response, MBTA Red Line service and bicycle and pedestrian access on the bridge at all times. Road and lane closures for materials delivery and equipment moves are scheduled during off-peak travel times to minimize traffic impacts.

The following elements of the project are complete:

• Installation of a new off-ramp from Storrow Drive to Charles Circle

• Reinforcing steel and cast-in-place concrete for seismic reinforcement of the 10 piers and two abutments

• Arch girder repairs

• Fabrication and installation of replica spandrel columns

• New floor beams, stringers, precast deck slabs and sidewalk framing

• Cleaning, repairing and re-installing replica cast iron fascia plates and ornamental pedestrian railing

• Installation of the reinforcing steel and cast-in-place concrete deck and sidewalk

• Removal, cleaning, repairing and re-installation of the four salt and pepper towers and the granite wall and cap stones

• Installation of the driven pile foundation and cast-in-place concrete for the new pedestrian bridge

• Installation of new MBTA, MassDOT and third party utilities

The current phase is due to be complete in June 2018, a three-month savings to the original schedule presented by WSC. At the conclusion of this phase MBTA Red Line Trains, vehicular, bicycle and pedestrian traffic will all be in their final positions.

A major problem for WSC has been the confined work area, which means that safety is a priority for workers and bridge users.

“There are restrictions and limited elbow room because the arches between the spans are staying in place, you can appreciate the level of tolerance and accuracy of how things were built in the early 1900s,” said McInerney. “When you tie into existing pieces of infrastructure, it becomes more challenging. Things have to line up and in many instances they don't.

“The original builders used riveted construction for all the steel — a hot rivet was placed and compressed to conform to a hole. When we removed the rivets to replace the deficient steel, they did not necessarily line up. We have to replace the rivets with bolts and the bolts have to fit into the diameter of the hole. Some of the holes had to be reamed out to make them true and lined up to not impact the sizing of the bolts.”

The historical status of the bridge requires that certain portions of the work are refurbished accurately, including spans 1, 2, and 11 that go over dry land. The use of rivets is required for these portions.

“Rivets have not been used since the 1960s and we had to get people at the fabrication facilities to learn how to install them,” said McInerney. “The rivets are heated up to 1,800 F and we've had a few issues with how this has affected the coating of the steel. As a result, some steel has had to be galvanized and painted on-site. Some of the work required revisions to meet historical requirements and at the same time meet today's codes and standards.”

Another challenge is the replacement of the steam line beneath the bridge that services local hospitals. This is a major part of the project, especially as it deals with temperature and pressure.

“We have to plan the replacement line carefully because once it leaves the bridge, it does a lot of twists and turns,” said McInerney. “It required a lot of reviews and analysis to make sure that it worked. As the new steam line was being installed, cutovers were required to transition the new to the old.”

Hazardous materials were also found during excavations to remove soil under the salt and pepper towers for upgrading the foundations.

“It was not foreseen,” said McInerney. “There were various levels of contamination and we changed our means and methods of work to keep some of the soil in place and remove the rest to proper disposal facilities.”

To avoid impacts on the subway during traffic shifts for new stages, WSC is utilizing temporary tracks on the road deck parallel to the two existing tracks (a shoo-fly) and uses them when work takes place close to or underneath the existing tracks.

Construction of the new pedestrian bridge connecting the Esplanade with Charles Circle began in November 2015, with work starting on the Esplanade side of Storrow Drive to the west of the existing bridge. It is scheduled to be complete in the summer of 2018.

The project will see the removal of 7,000 cu. yds. (5,351.8 cu m) of concrete; 3,700 tons (3,356.6 t) of asphalt; 2,900 tons (2,630.8 t) of structural steel; 525 tons (476 t) of rebar; and 7,200 cu. yds. (5,505 cu m) of earth. Crews will use 25,500 cu. yds. (19,496 cu m) of concrete; 13,500 tons (12,247 t) of asphalt; 2,900 tons (2,630.8 t) of structural steel; 2,300 tons (2,086.5 t) of rebar; 13,000 cu. yds. (9,939 cu m) of gravel; and 10,700 tons (9,706.8 t) of track ballast stone.

Materials that can be recycled are being maximized.

On an average day there are nearly 160 employees on site. Major subcontractors include: Atlantic Bridge and Engineering for structural steel fabrication and installation; STV Inc. for design services; Tri-State Painting; NASDI for demolition; Cianbro Fabrication and Coating for structural steel; Newport Industrial Fabrication for pedestrian bridge steel; and Saugus Construction for steel installation.

WSC is using a wide variety of equipment, including gantry cranes manufactured specifically for the rehabilitation of the roadway spans of the Longfellow. Barges with cranes are used for rehabilitation work from the water, including cleaning and painting the steel arches and removal and reinstallation of the salt and pepper shaker towers.

Special MBTA tie plates are being used on the permanent track to mitigate vibration on the bridge from the red line trains. Special molds and casting processes are used to replicate the cast iron fascia plates, ornamental railing and MBTA fence posts. Specialty repair/restoration work is being performed on the bronze doors that will be reinstalled in each tower.

Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA