List Your Equipment For Free  /  Seller Login

Solar Panels Now Offsetting Energy Costs at Takeuchi-US Facilities

Takeuchi-US has installed solar panels at their facilities in Georgia and South Carolina, offsetting 85% of energy needs. Remaining power sourced from green suppliers, making locations carbon neutral.

Thu July 25, 2024 - National Edition #17
Takeuchi


The first building to go live was Takeuchi's South Carolina office building in February 2024. That was followed by the training center (shown) in Pendergrass, Ga., and then the manufacturing plant in South Carolina.
Photo courtesy of Takeuchi
The first building to go live was Takeuchi's South Carolina office building in February 2024. That was followed by the training center (shown) in Pendergrass, Ga., and then the manufacturing plant in South Carolina.
The first building to go live was Takeuchi's South Carolina office building in February 2024. That was followed by the training center (shown) in Pendergrass, Ga., and then the manufacturing plant in South Carolina.    (Photo courtesy of Takeuchi) Takeuchi chose Renu Energy Solutions to install solar panels at both the Georgia and South Carolina facilities.    (Photo courtesy of Takeuchi)

Takeuchi is fully committed to being good global citizens who contribute to environmental preservation by developing and implementing sustainable technologies wherever and whenever possible.

Transforming Takeuchi facilities to carbon neutral was part of that plan, first in Japan and then in the United States. Recently, Takeuchi-US put that plan into action by installing energy-efficient solar panels at its locations in Pendergrass, Ga., and Moore, S.C.

The new solar panels will cover about 85 percent of the energy needs at those two facilities. The remaining 15 percent will be sourced as green energy from local electrical suppliers, allowing Takeuchi's U.S. locations to remain carbon neutral all year round.

To help offset the solar installation project's costs, Takeuchi will apply for tax credits that the Inflation Reduction Act provides for eligible renewable energy projects.

"We quickly learned that a solar project of this magnitude takes a lot of time and planning," said Angy Lamb, manager of operational services at Takeuchi-US. "We began meeting with solar energy companies in late summer 2022. Each company had to come on site to tour each building and evaluate the roof structures and electrical systems before drawing up preliminary design suggestions and providing estimates. That process alone took several months."

In March 2023, Takeuchi chose Renu Energy Solutions to install solar panels at both the Georgia and South Carolina facilities. The next project phase involved getting the appropriate permits from local government authorities as well as interconnection agreements with local power companies. Renu took care of those details, and in September 2023, all the necessary panels and hardware were shipped to Pendergrass and Moore. Soon after, Renu began installing the systems with almost no disturbance to business operations other than the final "tie-in" which requires a building's power to be shut down while the solar panels are connected to its electrical system.

Photo courtesy of Takeuchi

"The first building to ‘go live' was our South Carolina office building in February 2024," said Jeff Stewart, president of Takeuchi-US. "That was quickly followed by our Training Center in Pendergrass, Georgia and then the manufacturing plant in South Carolina. Finally, the machine distribution center, corporate office and main distribution center in Pendergrass came online in early July."

The solar panel installation project is just one example of Takeuchi's commitment to going green. The company also has converted its main distribution center in Georgia and plant in South Carolina to energy-efficient LED lighting, and its secondary distribution center is almost entirely illuminated by LEDs. Takeuchi's three-year-old training center in Georgia was built with all high-efficiency systems, including LED fixtures.

Later this year, Takeuchi will convert all lighting in its corporate offices over to LED, and in 2025, it will convert the remaining portion of the lighting in its secondary warehouse to LED, greatly reducing its electric bills.

"One element of Takeuchi's corporate commitment is cooperation," said Stewart. "In that commitment, we pledge to ‘thrive in conjunction with society, cultivating a mindset based on harmony and thoughtfulness.' We put this into action by partnering with the global community and by being good environmental stewards.

"Moving our facilities to a carbon-neutral position helps us live out our commitments and achieve our goals by being a better global partner. We try to take steps that will ensure the long-term success of not only Takeuchi, but also those who work with and around us."

For more information, visit www.takeuchi-us.com.




Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA