South Mountain Freeway Construction to Ramp Up in 2018

Tue February 27, 2018 - West Edition #5
Construction Equipment Guide


Work is currently under way in all but one section of the 22-mi. corridor.
(ADOT photo)
Work is currently under way in all but one section of the 22-mi. corridor. (ADOT photo)
Work is currently under way in all but one section of the 22-mi. corridor.
(ADOT photo) One year after major construction began on the Loop 202 South Mountain Freeway, bridges have been built from the ground up, a massive amount of earth has been moved and compacted, and an emerging I-10 interchange has changed the West Valley skyline.
(ADOT photo)

One year after major construction began on the Loop 202 South Mountain Freeway, bridges have been built from the ground up, a massive amount of earth has been moved and compacted, and an emerging I-10 interchange has changed the West Valley skyline.

The South Mountain Freeway is more than 35 percent complete from design to utilities to right-of-way acquisition to construction. Work is currently under way in all but one section of the 22-mi. corridor. To date, crews have installed 8 mi. of drainage pipe, moved 3.6 million cu. yds. of dirt and used 2,900 tons of rebar manufactured from recycled steel.

In 2018, construction will expand as the Arizona Department of Transportation moves toward opening the freeway by late 2019.

Work is scheduled to begin this spring in the Center segment, a 3-mi. stretch between 51st Avenue southeast and 32nd Lane.

ADOT and Connect 202 Partners, the developer responsible for the design and construction of the South Mountain Freeway, recently detailed construction for the first half of 2018 with the corridor's third semiannual construction notice, which is available at SouthMountainFreeway.com (click Construction Info).

Some of the 2018 highlights include:

I-10 segment (I-10 Papago to Lower Buckeye Road and improvements to I-10 between 43rd and 75th Avenues)

  • Constructing new access roads parallel to I-10 between 51st and 67th Avenues that will replace direct freeway access at 59th Avenue;
  • continuing construction of an I-10 interchange with six ramps, including two direct HOV lane connections; and
  • completing the bridge over Roosevelt Street.

Salt River segment (Lower Buckeye Road to 51st Avenue)

  • Opening an Elliot Road bridge over the freeway alignment;
  • starting Estrella Drive interchange construction, which will require a 150-day closure of Estrella Drive between 51st and 59th Avenues;
  • completing two half-mile-long bridges, the longest of project, over the Salt River (by end of 2018); and
  • constructing a bridge at Baseline Road and 51st Avenue.

Center segment (51st Avenue to 32nd Lane)

  • Conducting pre-construction work, including plant salvage and geotechnical investigations (starting in early 2018) and
  • starting controlled rock blasting along two ridges on southwestern edge of the South Mountain Park to break large rock into smaller, more manageable pieces.

Pecos segment (32nd Lane to I-10 Maricopa/Loop 202 Santan Freeway)

  • Detouring traffic on Desert Foothills Parkway for bridge construction;
  • completing bridges at 17th Avenue and 40th Street and continuing construction of bridges at 24th and 32nd streets, work that will require some weekend and night closures of cross streets;
  • beginning work on freeway paving (by late 2018); and
  • completing controlled rock blasting along Pecos Road between Desert Foothills Parkway and 24th Street to break large rock into smaller, more manageable pieces (through mid-2018).

The South Mountain Freeway will provide a long-planned direct link between the East Valley and West Valley and a much-needed alternative to I-10 through downtown Phoenix. Approved by Maricopa County voters in 1985 and again in 2004 as part of a comprehensive regional transportation plan, the South Mountain Freeway will complete the Loop 202 and Loop 101 freeway system in the Valley.

For more information, visit SouthMountainFreeway.com.




Today's top stories

Construction Industry Optimistically Preparing for New Year Ahead

CFX Oversees $412M SR429 Expansion in Florida

Capital Express Central Project Ramps Up in Texas

VIDEO: NCDOT Plans Major Road Upgrades in Wilmington Over Next Several Years

DEVELON Set to Exhibit at ARA Show 2025

Des Moines Airport Works With Weitz/Turner On Expansion

Ring Power Lift Trucks Partners With Hiab to Bring MOFFETT Truck-Mounted Forklifts to Florida Customers

Earthborne Demo Day Draws Crowd Despite Downpour


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA