List Your Equipment For Free  /  Seller Login

Three Projects Share Glory on Award-Winning Steel Projects

Thu May 24, 2018 - National Edition
Steel Erectors Association of America


Gardner-Watson Decking Inc. installed 1.5 million sq. ft. of deck in four weeks on Project Red.
Gardner-Watson Decking Inc. installed 1.5 million sq. ft. of deck in four weeks on Project Red.
Gardner-Watson Decking Inc. installed 1.5 million sq. ft. of deck in four weeks on Project Red. Buckner Companies constructed the dome for Holy Name of Jesus Cathedral on the ground then lifted it using special rigging and a Liebherr LR/1400 crawler crane. JP Cullen erected about 8,000 tons of structural steel to build a new 730,000 sq. ft. Milwaukee Bucks Arena.

An independent panel of judges on behalf of The Steel Erectors Association of America selected three steel construction projects for the association's annual projects of the year. Teams from Gardner-Watson Decking (Class I for erection contracts up to $500,000), Buckner Companies (Class III above $1 million to $2.5 million), and J.P. Cullen & Sons (Class IV over $2.5 million) were honored at SEAA's 2018 annual convention, held in April in Greensboro, N.C. No awards were granted in the Class II category ($500,000 to $1 million) for 2017.

The winning projects demonstrate the range and complexity of steel construction in the United States. One project was a steel decking job on a massive distribution for a retail company ruled by capitalism and the Almighty Dollar. The other two jobs were temples of worship — one to God and the other the NBA's Milwaukee Bucks.

The winner in Class I was for a job called Project Red, Louisville, Ky. Gardner-Watson Decking Inc. installed 1.5 million sq. ft in four weeks, nearly three weeks faster than estimated on a distribution center for a retail construction products company. To do so, Gardner-Watson Decking put a premium on safety in order to eliminate downtime due to injuries and scaled its manpower according to the pace of the steel erection.

“The schedule was aggressive and in order to meet or beat the schedule, erector Premier Steel focused on steel erection while G-W Deck focused on deck installation. Coordination between the two companies was essential to the project's success,” said Geoff Kress, vice president, Gardner-Watson Decking.

The winning Class III project, Holy Name of Jesus Cathedral, Raleigh, N.C., is one of the six largest cathedrals in the United States. Featuring brick and masonry exterior with precast accents, the highlight of the building is the copper dome, which also presented the biggest erection challenge for Buckner Companies. The dome was constructed on the ground then lifted using special rigging designed by Buckner using a Liebherr LR/1400 crawler crane with heavy lift attachment.

“The planning and effort required to successfully construct the massive dome on the ground, allowing for the installation of light gage framing, sheathing, decking and copper roofing, sprinklers, catwalk and even windows prior to erecting the dome in place, was extraordinary,” one of the judges said.

In the Class IV category, JP Cullen erected about 8,000 tons of structural steel to build a new 730,000 sq. ft. Milwaukee Bucks Arena, Milwaukee, Wis. The steel construction consisted of structural column and beam steel framing for the surrounding bowl structure including six levels plus a roof. The long span room consisted of nine long span roof trusses, approximately 33 ft. deep, with the longest truss spanning 313 ft..

Three things in particular contributed to successful completion three weeks ahead of schedule. First, there were several project specific situations where safety intervention occurred by ironworkers to abate unsafe scenarios. Second, steel erection was the critical path to an aggressive schedule, which JP Cullen overcame by working with the design team and construction manager to develop a temporary erection plan. Third was overcoming congestion and space constraints for people and equipment both inside and outside the bowl of the arena. Extensive planning, sequencing, and coordination was the solution.

For more information, visit www.seaa.net.




Today's top stories

Construction Industry Optimistically Preparing for New Year Ahead

CFX Oversees $412M SR429 Expansion in Florida

Capital Express Central Project Ramps Up in Texas

VIDEO: NCDOT Plans Major Road Upgrades in Wilmington Over Next Several Years

DEVELON Set to Exhibit at ARA Show 2025

Des Moines Airport Works With Weitz/Turner On Expansion

Ring Power Lift Trucks Partners With Hiab to Bring MOFFETT Truck-Mounted Forklifts to Florida Customers

Earthborne Demo Day Draws Crowd Despite Downpour


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA