VIDEO: Three Years In, North Hero-Grand Isle Bridge Remains On Track

Wed August 25, 2021 - Northeast Edition #18
Lori Tobias – CEG Correspondent



In recent months, crews with Cianbro excavated lake-bottom sediments from inside the cofferdams. Cianbro recently excavated lake-bottom sediments from inside the cofferdams and cleaned bedrock in preparation for placing the subfootings for two bascule piers. Cianbro will continue work on the piers through the summer, then begin structural steel erection in the fall. The project was held up earlier this year after hazardous materials, including lead, PCBs and hexavalent chromium were discovered during excavation. When completed, the North Hero-Grand Isle bridge in Vermont will link two islands on Lake Champlain. Crews are three years into a $60 million project to replace the North Hero-Grand Isle bridge in Vermont. The bridge is on schedule to be operational by May 15, 2022. The project is scheduled to be complete by July 2023. Cianbro plans to continue work on the piers through the summer, then begin structural steel erection in the fall.

Three years into a $60 million project to replace the North Hero-Grand Isle bridge in Vermont, crews are pouring concrete with an eye toward building the new replacement drawbridge in the 2022.

The bridge links two islands on Lake Champlain. Progress was slowed earlier by the unexpected discovery of hazardous contaminants, but the materials have been safely removed and work is back on track.

"Things are going well," said Jacqueline Dagesse, spokeswoman of the Vermont Agency of Transportation (VTrans). "We have deconstructed the original drawbridge, constructed the temporary drawbridge now in operation, and we are focused on multiple concrete pours for the bridge substructure. The bridge is on schedule to be operational by May 15, 2022. The project is scheduled to be complete by July 2023."

In recent months, crews with Cianbro excavated lake-bottom sediments from inside the cofferdams and cleaned bedrock in preparation for placing the subfootings for two bascule piers, said Taylor Ware, VTrans resident engineer. Each subfooting was poured via tremie with 1,000 cu. yds. of concrete for each subfooting. Each tremie placement required 13 continuous hours of concrete work. After the bascule pier subfootings were complete, the cofferdams were dewatered and rock anchors installed to withstand buoyant forces on the dewatered cofferdam. Cianbro crews next erected formwork, installed rebar and poured the bascule pier footings, each about 680 cu. yds. of concrete. Once bascule pier footings were complete, they began building the reinforced concrete walls of the bascule piers and supports for the bascule spans.

"The piers are hollow, the equivalent of a three-story reinforced concrete building," Ware said. "The piers will be constructed in three lifts. The contractor is currently working on lift two of each [second story] bascule pier. The two bascule piers will house all of the electrical and mechanical equipment as well as the trunnions and counterweights for the new bascule spans."

Cianbro plans to continue work on the piers through the summer, then begin structural steel erection in the fall.

Earlier this year, crews placed concrete for the second lift of the north horseshoe section and installed reinforcing steel and forms for the south section. On the west side of the existing bridge, the contractor installed formwork and placed concrete for the south horseshoe-shaped section for the second lift of the pier walls. Crews also installed the last of the reinforcing steel and anchor bolts for the north half of the second lift of the pier walls. On the east side of the existing bridge, the contractor installed the last of the reinforcing steel and anchor bolts for the north half of the second lift of the pier walls.

Cianbro currently has two Manitowoc 4100 cranes, FlexiFloat barges and steel concrete forms, which were rented.

The project was held up earlier this year after hazardous materials, including lead, PCBs and hexavalent chromium were discovered during excavation. VTrans engineers believed the contaminants may have come from the sandblasting and painting decades ago of the old bridge railing.

The drawbridge operates only five months of the year, from May 15 to Oct. 15 during boating season. The rest of the year, the bridge remains in the down position to maintain vehicle traffic.

The original historic twin bascule bridge was built in 1953 and was the main road through the island, seeing approximately 3,000 cars daily during the off season and double the number in the summer and fall. The bridge also provides the only unrestricted access for boats and is the only route big sailboats can get through.

The new bridge will have some significant differences from the one it is replacing. Instead of electrical motors that had to be cranked, the new bridge will open and close on a hydraulic system. The new deck will feature stainless steel reinforcement steel, which is anticipated to lengthen the lifespan. Instead of pavement, there will be concrete and the bulk of the girders will be metalized rather than painted, and some smaller pieces will be galvanized. When complete, the new bridge is expected to last 75 to 100 years. CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA