List Your Equipment For Free  /  Seller Login

Two-Crane Solution Solves Access Challenge When Building Inside Old Natatorium

Wed May 22, 2024 - Midwest Edition #15
ALL Crane


Set up outside was a Liebherr LTC 1050 all terrain crane. With three axles and a 50-ton capacity, it drives more like a truck crane.
Photo courtesy of ALL Crane
Set up outside was a Liebherr LTC 1050 all terrain crane. With three axles and a 50-ton capacity, it drives more like a truck crane.
Set up outside was a Liebherr LTC 1050 all terrain crane. With three axles and a 50-ton capacity, it drives more like a truck crane.   (Photo courtesy of ALL Crane) The Liebherr LTC 1050's job was to pick planks off the delivery truck, boom each piece through a doorway and set it on the floor.   (Photo courtesy of ALL Crane) A 25-ton Broderson IC-400 carry deck crane drives to the doorway, picks up the piece, performs a pick and carry to the set position, then deploys its outriggers before setting the piece.   (Photo courtesy of ALL Crane) The Broderson IC-400 employed three different load charts for each pick: pick and carry on rubber, intermediate outriggers and full outriggers.   (Photo courtesy of ALL Crane) The capacities and radii necessary limited the size of each plank to 21 ft. long and 4 to 5 ft. wide, with weights of approximately 6,000 lbs. Mack Industries custom-cast each piece especially for the job.   (Photo courtesy of ALL Crane)

Converting an indoor swimming pool in Lorain, Ohio, into a meeting area and classrooms was going to take precast planks. However, there was no obvious way to get the planks inside the existing, about-to-be-transformed natatorium structure.

Not only could a delivery truck not back into the building because there was no doorway large enough, even if it could, the placement of stairwells and other interior elements would have made navigation impossible.

So, what to do? ALL Erection & Crane Rental, a member of the ALL Family of Companies, worked with precast manufacturer Mack Industries on a novel solution for contractor John G. Johnson Construction.

ALL started by determining what lift equipment could fit inside the building, and Mack reverse-engineered its precast planks to suit the resulting radii and capacities.

Brian Meek, sales rep of ALL Erection & Crane Rental, said they landed on the unique solution of using two pieces of lift equipment — one outside the building, and a carry deck inside — to "hand off" each precast plank.

Set up outside was a Liebherr LTC 1050 all terrain crane. With three axles and a 50-ton capacity, it drives more like a truck crane. Its job was to pick planks off the delivery truck, boom each piece through a doorway, and set it on the floor. Then a 25-ton Broderson IC-400 carry deck crane took over.

"The Liebherr lays down the precast, the Broderson drives to the doorway, picks up the piece, performs a pick and carry to the set position, then deploys its outriggers before setting the piece," Meek explained.

It's a complex series of steps, one that required the Broderson to employ three different load charts for each pick: pick and carry on rubber, intermediate outriggers and full outriggers.

The capacities and radii necessary limited the size of each plank to 21 ft. long and 4 to 5 ft. wide, with weights of approximately 6,000 lbs. Mack Industries custom-cast each piece especially for the job.

The carry deck crane was, of course, building new interior walls for classrooms while also being confined by the already-existing walls of the natatorium. Eventually, it would be sandwiched between both walls. This limited the reach, and the near radius was limited by the presence of the ceiling, so the plank couldn't be lifted too closely, either.

Because of a well-thought-out plan, ALL worked with Mack Industries to set the 30 precast planks in less than two full days.

"Carry decks aren't often used on construction projects, but they are ideal for work on flat, concrete surfaces, like industrial plant operations," said Meek. "Because we were unable to drive the precast directly into the building as we typically do on this kind of project, the Broderson was a perfect solution working in tandem with the Liebherr LTC 1050."

For more information, visit www.allcrane.com.

This story also appears on Crane Equipment Guide.




Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA