List Your Equipment For Free  /  Seller Login

Union Paving Begins Portion of NJDOT's $155M Job

Thu December 31, 2020 - Northeast Edition #1
Irwin Rapoport – CEG Correspondent


Stage 5 will complete the reconstruction of the proposed Route 46 median barrier from east of Lower Notch Road to Route 3, construct the proposed Valley Road southbound widening between Route 46 and Robin Hood Road, demolish the existing Route 46 eastbound bridge over Ramp K and complete the Route 46 median barrier to St. Philip Drive.
Stage 5 will complete the reconstruction of the proposed Route 46 median barrier from east of Lower Notch Road to Route 3, construct the proposed Valley Road southbound widening between Route 46 and Robin Hood Road, demolish the existing Route 46 eastbound bridge over Ramp K and complete the Route 46 median barrier to St. Philip Drive.
Stage 5 will complete the reconstruction of the proposed Route 46 median barrier from east of Lower Notch Road to Route 3, construct the proposed Valley Road southbound widening between Route 46 and Robin Hood Road, demolish the existing Route 46 eastbound bridge over Ramp K and complete the Route 46 median barrier to St. Philip Drive. Union Paving & Construction Co. Inc. (UPC) started work on Contract B ($155.4 million) of the New Jersey Department of Transportation’s (NJDOT) $218.5 million project to reconstruct the Route 3, Route 46, Valley Road and Notch/Rifle Camp Road interchanges. The design life for the new infrastructure — bridges, ramps, etc. — is 100 years.

Union Paving & Construction Co. Inc. (UPC) started work on Contract B ($155.4 million) of the New Jersey Department of Transportation's (NJDOT) $218.5 million project to reconstruct the Route 3, Route 46, Valley Road and Notch/Rifle Camp Road interchanges last February.

Contract A (approximately $62.6 million), financed by federal and state funds, and Contract B, federally funded, were initiated to correct existing operational and safety problems.

"These existing problems along the Route 46 and Route 3 corridors have resulted in a high occurrence of accidents and chronic bottlenecks," said Steve Schapiro, NJDOT's deputy director of communications. "The problems being addressed are inadequate acceleration and deceleration lanes, narrow shoulder widths, closely spaced driveways and access points, poor sight distance, reduced lanes on Route 3 westbound and deteriorated and substandard bridges."

When completed, traffic flow will improve and fewer idling vehicles is expected to decrease air pollution.

"The interchanges are geometrically deficient and create a major bottleneck for vehicles traveling in either direction," said Schapiro. "Heavy traffic volume during peak periods, and inadequate or nonexistent acceleration and deceleration lanes and shoulders lead to irregular driver maneuvers. The new on- and off-ramps at the interchanges will include exclusive left-turn lanes at the terminals and traffic signals will have coordinated timing to provide an optimum level of service."

The project is taking place in the city of Clifton, township of Little Falls and the borough of Woodland Park in Passaic County; and the work zone extends from Route 46 from just east of Browertown Road (milepost 58.76) to Rock Hill Road (milepost 60.58) and along Route 3 from the Route 3/Route 46/Valley Road interchange (milepost 0.00) to just east of Grove Street (Milepost 0.63).

A feasibility assessment study was completed in 2001 to determine the transportation problems and needs along Route 46 from the interchange with Notch and Rifle Camp Roads in Little Falls and Woodland Park to the Route 3/Valley Road Interchange in Clifton, and the preliminary design phase was completed and approved in June 2008.

"This resulted in the development of the proposed improvement plan, which successfully reduced both utility and environmental impacts," according to NJDOT.

Contract A, awarded to Creamer-Sanzari, a joint venture (J. Fletcher Creamer & Son and Joseph M. Sanzari Inc.), began in spring 2016 and was completed in fall 2019. It included the construction of the new Great Notch Road, a new bridge over Route 46 from Great Notch Road to Clove Road, three signalized intersections, two single-lane roundabouts parallel to Route 46 westbound to remove local traffic from the state highway, the relocation of major city of Newark and Passaic Valley Water Commission water mains along the north side of Route 46, construction of the new Clove Road overpass and interchange ramps and the reconstruction of the existing Notch Road Bridge.

Contract B calls for realigning and widening Route 46, as well as the construction of wider shoulders, acceleration, deceleration and auxiliary lanes. At the Route 3/Route 46 interchange, a three-lane Route 3 section will replace the existing two lane connections, and Route 46 will be realigned to better converge with Route 3. The new interchange includes four new bridge structures, a new signalized intersection, and a new multi-lane roundabout. This work is anticipated to be complete in 2024. Contract B's infrastructure was designed by Stantec.

The design life for the new infrastructure — bridges, ramps, etc. — is 100 years.

"The deck slabs and parapets are constructed with HPC [high performance concrete] for enhanced durability," said Brian Ahrens, an NJDOT public information officer.

The traffic management plan is based on daytime and evening temporary lane and ramp closures and detours as the work progresses. An example of that was the traffic shift, which occurred on April 22, assisted by the New Jersey State Police, that allowed UPC to widen Valley Road to prepare for the construction of a roundabout at the Valley Road/Great Notch Road intersection.

A construction analysis of the project determined that it should be divided and that the phasing for each contract stress utility relocation needs and the prioritization of improvements.

Contract B is being constructed in six stages, Stage 1, with sub-stages 1A, 1B and 1C, had crews constructing the Route 3 eastbound widening, noise barrier and retaining wall from behind the construction barrier, building the Ramp H and the Ramp I bridge; widening Valley Road at Great Notch Road; remove the existing Route 46 median barrier and constructing temporary pavement for the Stage 2 traffic shift; and widening Route 46 westbound east of the interchange.

Stage 2 covers the eastbound widening of Route 46 from Lower Notch Road to Route 3 from behind construction barrier, constructing the west side of new Route 46 bridge over Lower Notch Road and the new Route 46 bridge over Valley Road; reconstructing the existing Route 46 eastbound ramp to Valley Road (Ramp G) and constructing the proposed Route 46 eastbound flyover ramp and bridge structure, the existing Route 3 median barrier from Route 46 to Grove Street, and the existing Route 46 median from St. Philip Drive to Rock Hill Road; activating the temporary traffic signal on Valley Road; and continuing the reconstruction of the Valley Road/Great Notch Road Intersection for the future multi-lane roundabout.

Stage 3 will deal with the shifting of Route 46 eastbound traffic to the widened section and constructing the proposed median; continuing construction of the new Route 46 bridge over Valley Road and northern portion of the Route 46 Bridge over Lower Notch Road; opening the new Route 46 eastbound flyover bridge and the new ramp to Valley Road (Ramp G); shifting Route 3 eastbound traffic to the temporary connector roadway; constructing the proposed eastbound connector roadway and continuing to reconstruct the existing Route 3 median barrier from Route 46 to Grove Street, as well as the Valley Road/Great Notch Road intersection.

Stage 4 will construct the center portion of the Route 46 Bridge over Lower Notch Road; shift Route 46 traffic south and construct the proposed Route 46 westbound widening from behind barrier; construct the new Route 3 westbound ramp to Valley Road (Ramp K) and the new Route 46 westbound bridge over Ramp K, the north side of the new Route 46 Bridge over Valley Road and the remaining portions of the Valley Road roundabout; and reconstruct the westbound side of Route 3 from behind barrier between Grove Street and proposed Ramp K.

Stage 5 will complete the reconstruction of the proposed Route 46 median barrier from east of Lower Notch Road to Route 3, construct the proposed Valley Road southbound widening between Route 46 and Robin Hood Road, demolish the existing Route 46 eastbound bridge over Ramp K and complete the Route 46 median barrier to St. Philip Drive.

The final stage will see the installation of the final overhead guide sign panels, open all roads/ramps/lanes to traffic, and complete final paving, striping, ground-mounted sign installation and landscaping.

Night work conforms to local ordinances. New underground utilities (minor water mains, gas mains, electric, telephone and cable conduits) are being constructed by UPC, with aerial facilities relocated by individual utility companies.

UPC is constructing one new Third River culvert and extending two existing culverts, and associated drainage facilities (inlets, pipes, outfalls, etc.) installations include two storm water management basins and subsurface detention systems. It also is replacing three bridges at the Route 46 and Route 3 interchange for the reconfiguration of ramps to meet current standards, as well as the existing Route 46 bridge over Lower Notch Road.

Crews are now engaged in Phase 2, with a focus on road and bridge work.

"Like any project in a densely populated and congested area, Contract B needed to be designed to address challenges such as utility conflicts, right-of-way and restricted work areas all while maintaining traffic through a busy commuter corridor with minimum disruption," said Ahrens. "In addition, the project goes through multiple towns requiring close coordination with many stakeholders. These issues were carefully considered during the final design phase to ensure that any mitigation strategies would have a minimal effect on the project's scope, schedule and cost. Weather can present challenges with any project, and the Route 3/Route 46 Interchange Improvement Project is no exception. The project was designed so that paving and other weather-sensitive stages could be completed during the warmer months."

Currently UPC is working on installing storm sewers, telecommunication conduit, 16-in. water main and electrical conduit, and in terms of road work, engaged in grading, roadway excavation and construction and paving.

"They are also installing panels for sign structures, drilling for noise walls and retaining walls, and setting panels for noise walls," said Ahrens. "They are also working on Valley Road bridge, Lower Notch bridge, Valley Road northbound ramp over Route 46 connector bridge and Route 46 eastbound bridge [working on abutments, wingwalls and backwalls]."

The general contractor is building 18 retaining walls, four noise walls and 13 sign support structures. Peak days thus far have many UPC and subcontractor (local and regional) employees on site.

The amount of material being removed by earthwork and excavation operations — earth and rock, concrete, asphalt and steel — are still being tabulated.

A considerable amount of new material is being brought in, including: 117,911 tons of asphalt (some of this is temporary for staging, etc.), 263,000 lbs. of structural steel (steel beams) and 148,400 lbs. of rebar for the Lower Notch bridge, 891,000 lbs. of structural steel (steel beams) and 372,400 lbs, of rebar for the Valley Road bridge, 297,000 lbs. of structural steel (steel beams) and 177,800 lbs. of rebar for the Route 46 westbound over Route 3 westbound to Valley Road ramp, 2,462,500 lbs. of structural steel (steel beams) and 399,900 lbs. and rebar for the Route 46 eastbound over Route 3 westbound to Valley Road ramp and connectors bridge, and 530,000 lbs. of structural steel (steel beams) and 192,700 lbs. of (rebar) for the alley Road northbound ramp over Route 46 connector bridge.

UPC and the subcontractors are using cranes, excavators, dozers, loaders, motorgraders, rollers, pavers, milling machines, and other standard equipment purchased and rented from area dealerships. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Construction Industry Optimistically Preparing for New Year Ahead

CFX Oversees $412M SR429 Expansion in Florida

Capital Express Central Project Ramps Up in Texas

VIDEO: NCDOT Plans Major Road Upgrades in Wilmington Over Next Several Years

DEVELON Set to Exhibit at ARA Show 2025

Des Moines Airport Works With Weitz/Turner On Expansion

Ring Power Lift Trucks Partners With Hiab to Bring MOFFETT Truck-Mounted Forklifts to Florida Customers

Earthborne Demo Day Draws Crowd Despite Downpour


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA