List Your Equipment For Free  /  Seller Login

USACE Plans Jetty Projects Along Oregon Coast

Tue December 18, 2018 - West Edition #26
Lori Tobias – CEG Correspondent


Larger barges can carry nearly 14,000 tons, the equivalent of 500 truck loads.
Larger barges can carry nearly 14,000 tons, the equivalent of 500 truck loads.
Larger barges can carry nearly 14,000 tons, the equivalent of 500 truck loads. Jetties help stabilize the bar by creating a channel for boats to transit and also by allowing the water to carry sediment out to sea, reducing the need for dredging.
 “Eighty percent of the cost of building a jetty is producing the stone and shipping it,” said Jerry Otto, project manager of the Army Corps of Engineers.  
 The jetties on the Columbia River, originally built in 1885, transformed the mouth from a 5-mi. opening to a 2-mi. opening.  Armor stones weigh anywhere from four to 38 tons each. The armor stones are carefully placed and must have contact at the side, top and bottom of the stone next to it.
 Jetties are built with tons of massive armor rock on the exterior and smaller rock, of lesser quality on the inside. Jetties help stabilize the bar by creating a channel for boats to transit and also by allowing the water to carry sediment out to sea, reducing the need for dredging.
 “There are multiple quarry sources from Washington into California along the Pacific Coast that produce a basalt type of stone that has a good density to it,” said Jerry Otto, project manager of the Army Corps of Engineers.

The U.S. Army Corps of Engineers recently held an Oregon Coast Jetties Industry Day, gearing up for a series of jetty and breakwater projects expected to keep construction crews working through 2022. The projects include the complete rehabilitation of three jetties at the mouth of the Columbia River; repair of the Tillamook Jetties; the Coos Bay North Jetty; and the Port Orford breakwater.

Over the last few years, this is the third Industry Day we've had," said Jerry Otto, project manager of the Corps. "Because we had the authorization to rehab the jetties at the mouth of the Columbia River, and we also have these others, it is good timing to make sure the industry knows not only is the South Jetty at the mouth of the Columbia coming, but now we have Tillamook and Coos Bay and Port Orford coming up, too. We want to make sure the industry is aware and can start planning for this work. We can't do these projects without these folks. We really try to communicate to them as early as possible when we know there is some certainty that we have funding to do these projects."vt

Jetties help stabilize the bar, that place where the ocean collides with the flat water of the bay, by creating a channel for boats to transit and also by allowing the water to carry sediment out to sea, reducing the need for dredging. The bar is generally considered the most dangerous place for a boat going out to sea.

The jetties on the Columbia River, originally built in 1885, transformed the mouth from a 5-mi. opening to a 2-mi. opening. More than 2,000 ships have been lost at the mouth because of the unpredictable bars.

Jetties are built with tons of massive armor rock on the exterior and smaller rock, of lesser quality on the inside. It's an effort that takes time, planning and many, many millions of dollars. Jetty A, at 0.9 mi., the smallest of the three jetties at the mouth of the Columbia River, cost $20 million; while the 2.5-mi.-long N. Jetty is expected to cost $30 million. Specifications for the S. Jetty, which juts 6.3 mi. out to the sea are still being designed.

Armor stones weigh anywhere from four to 38 tons each, Otto said. "We require the contractors to individually place these armor stones. There are multiple quarry sources from Washington into California along the Pacific Coast that produce a basalt type of stone that has a good density to it. We don't really use granite because granite is less dense than basalt. Sometimes it has to come from several hundred miles away."

Some quarries use geophysical investigation to help determine how to blast the rock, while others work solely from experience and an understanding of the terrain. Once the stone is available, the contractors generally truck the stone to the port, then use barges to float it to the jetty site. Larger barges can carry nearly 14,000 tons, the equivalent of 500 truck loads.

"There is a tremendous amount of waste material that comes with getting those big stones," Otto said. "Eighty percent of the cost of building a jetty is producing the stone and shipping it. Twenty percent of the cost is placing it at the site. They have some large loaders, like the Cat 990 loader that can lift these larger stones, and Cat 773 haul trucks that they use to haul the stones. If they are delivering by land, they use low-boy semis. That's mostly what the public sees. On some of those stones, the ones up to 30 tons, there is just one stone per truck. The stone sizes will vary. The bigger ones will go where the sea is roughest. Smallest, at root of jetty connected to land."

The armor stones are carefully placed and must have contact at the side, top and bottom of the stone next to it, he said.

"It's a jigsaw puzzle. It doesn't go very fast. When you are trying to get something to last 50 years in those conditions out there you are going to take the time to do it right."

The Project Details

Jetties at the mouth of the Columbia River: Jetty A has been completed, the North Jetty is under construction and the Corps anticipates releasing requests for proposals for the South Jetty rehabilitation project in winter 2018-2019.

The current estimated stone quantity for South Jetty is 360,000 tons. Of this quantity, approximately 30 percent will be high-density stone with a minimum unit weight of 180 lbs/cu.ft. The stone placement period of performance will run five years through October 2024.

Tillamook Jetties: The Corps has contracted out an engineering report to further develop the repair design for the South Jetty and a portion of the North Jetty at the root. The Corps currently anticipates releasing requests for jetty repair sometime between fiscal year 2020 and 2022, dependent on funding availability.

The current planning estimate for stone quantities ranges from 80,000 to 120,000 tons depending on rate of jetty degradation and final design. High-density stone (greater than 175 lbs. per cu. ft.) is expected to be required for at least 1/3 of the stone volume.

Coos Bay North Jetty: The Corps will complete an engineering design report in fiscal year 2018 to further develop the repair design for the North Jetty Head, Jetty Root, and shoreline fill along Log Spiral Bay. The Corps currently anticipates releasing requests for jetty repair sometime between fiscal year 2020 and fiscal year 2022, dependent on project sequencing and funding availability.

The current planning estimate for stone quantities is approximately 100,000 tons depending on rate of jetty degradation and final design. High-density stone (greater than 175 lbs. per cu. ft.) is expected to be required for 10-15 percent of the total stone volume.

Port Orford Jetty: The Corps received funding in fiscal year 2018 to award the construction contract for the breakwater repair. The Corps currently anticipates releasing requests for proposals for the Breakwater repair in first quarter FY19.

The current planning estimate for stone quantities is 25,000 to 30,000 tons of new jetty stone procurement and placement. High-density stone (greater than 175 lbs. per cu. ft.) is expected to be required for at least half of the stone volume.

CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

SEPTA Builds Major Transportation Center

National Equipment League — Heavy Equipment Operation as a Professional Sport — Launches Season Two

Washington Bridge in Providence, R.I., Undergoes Demolition

Construction Industry Optimistically Preparing for New Year Ahead

Capital Express Central Project Ramps Up in Texas

Nevada DOT Awards $54M Contract for U.S. 50 Renovation in Ely

Construction Set for $37M Wildlife Crossing in Wyoming

PCL Construction's Special Projects Division Sets 2024 Record With Nearly 270 New Projects


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA