List Your Equipment For Free  /  Seller Login

VDOT's $58M Jones Branch Connector Project Proceeds According to Schedule

Wed May 23, 2018 - National Edition
Irwin Rapoport – CEG Correspondent


Archer Western Contractors LLC crews continue work on the VDOT Jones Branch Connector project.
Archer Western Contractors LLC crews continue work on the VDOT Jones Branch Connector project.
Archer Western Contractors LLC crews continue work on the VDOT Jones Branch Connector project. The Connector is expected to relieve traffic along Route 123, at the I-495 interchange and at other congested intersections. 
 On the average day, 40 construction workers can be found on site.
 The project will see the installation of 11,000 tons of asphalt, 36,000 sq. ft. of retaining walls, 755,000 lbs. of reinforcing steel and 6,000 cu. yd. of concrete for bridge structures.
 Once completed, the bridges and walls are expected to have a service life of 75 years.

Crews from Archer Western Contractors LLC began work in January 2017 on the Virginia Department of Transportation's (VDOT) $58 million Jones Branch Connector project that will connect Jones Branch Drive to Route 123 (0.5-mi.) in Northern Virginia's Fairfax County.

The plan is to partially open the road to traffic in late 2018, with final completion expected in late 2019.

"This project, in cooperation with Fairfax County, will provide an important new link to Route 123 over the Capital Beltway [I-495] for commuters and visitors to Tysons," according to the project web page. "The link will improve local traffic and access for drivers, as well as provide a vital option for area bicyclists and pedestrians."

The project includes: a new roadway from the interchange of the I-495 express lanes and Jones Branch Drive to Scotts Crossing Road; improvement along the access road from Jones Branch Drive to the express lanes, as well as along Scotts Crossing Road; two travel lanes and on-street bike lanes in each direction; three bridges over the I-495 express and general-purpose lanes; eight- to 12-ft. wide lighted sidewalks; landscaping and other streetscape amenities; and a wide, raised median to accommodate the future transit.

"By providing an alternate route across the Beltway and linking the Tysons East and Central areas, the Connector is expected to relieve traffic along Route 123, at the I-495 interchange and at other congested intersections," the web page said. "The road is expected to carry more than 32,000 vehicles per day by 2040."

Fairfax County has been planning this project since 2011.

"There can be no direct comparison of drivers' experiences before and after the project as it is literally creating a brand-new connection in Central Tysons," said Ellen Kamilakis, a VDOT senior public affairs officer. "Before the project, drivers had to navigate several roads before connecting to Route 123. Planning for multiple transportation modes was successfully achieved through a close working partnership with Fairfax County, who designed the project, and other stakeholders. VDOT's Northern Virginia District encompasses four counties, and the agency works hand-in-hand daily with local transportation agencies."

The project is being completed through a combination of federal, state and county funds. Fairfax County led design and development, with VDOT managing the construction process.

The design was prepared by Johnson, Mirmiran & Thompson.

"The bridges and walls are designed to meet VDOT design guidelines and standards," said Kamilakis. "As such, they are expected to have a service life of 75 years. Pavements, including sidewalks, will require normal periodic maintenance to exceed the 75-year service life. It is not unusual for drainage and other utilities to remain in service beyond 75 years.

"The two western bridges, already in place, are being widened," added Kamilakis. "They are both steel plate girder bridges with MSE abutments. We matched the existing design to widen in-kind for the two western bridges which also eased construction impacts to Beltway traffic. The longer bridge spanning over northbound I-495 also lends itself to steel girder construction and it was developed as a steel girder bridge to match the other two bridges."

The traffic impacts include nighttime lane closures on I-495 (Capital Beltway) and the I-495 express lanes as steel beams are installed. There will be additional lane closures as needed on Dolly Madison Boulevard, Scotts Crossing Road and Jones Branch Drive. The lane closures cover non-rush hour periods during the day and longer periods at overnight, often between 10 p.m. and 5 a.m.

A key aspect of the traffic management plan is ensuring that access to all businesses is being maintained throughout the construction.

"Safety of all of the users of the new bridges is paramount," Kamilakis said. "By adhering to the Tysons Urban Design Standards, the project is not only bicyclist and pedestrian friendly, but it also accommodates future transit. By having overnight and off-peak lane closures, we reduce the impact on drivers and businesses in the immediate area. Work zone safety is a year-round focus for VDOT. Drivers who are distracted or intoxicated pose a serious safety risk for crews working on the project. VDOT asks that all drivers stay focused while driving and pay special attention to work zone signs."

March was a busy time for the crews as steel beam placement for the bridge over I-495 began; abutment and retaining wall work continued; and installation of ITS systems, traffic signal work, light pole foundation work along Scotts Crossing Road and sound wall work along I-495 continued.

Archer Western has set the beams on two of the three bridges.

"An interesting challenge with the project comes with its location, adjacent to the construction of Capital One's new corporate headquarters," said Kamilakis. "Communication and coordination amongst stakeholders have ensured that it has been a seamless working relationship. There is essentially one big work site, although it is three bridges. The general contractor suggested combining portions of phase one with portions of phase two, which was implemented — thus optimizing the contractor's productivity.

"Communications with the general contractor continue to be open, productive and ongoing," she added. "The project is considered to be one big team. There is only a minimal amount of roadwork with this project. There are several mechanically stabilized earth [MSE] walls in various locations of the project."

Putting up three bridges is no easy task.

"A challenge related to utilities came in the form of a gas line whose proximity to bridge substructure elements necessitated the use of deep foundations that minimized/eliminated vibration in the vicinity of said existing gas line," said Kamilakis. "While typical modifications to existing bridges usually involves the widening of an existing structure, one of the existing bridges on this project was both widened and lengthened. Lengthening of the existing bridge was anticipated during the design of the existing bridge.

"In anticipation of future lengthening of the bridge, the west abutment of the existing bridge was designed and detailed in a manner that will permit a future conversion to a bridge wall pier with minimal modification," she added. "A link slab was introduced over the newly converted wall pier to eliminate the need for an expansion joint between the existing span and the new span."

Of the many subcontractors working on the project, the major ones include: A-Annandale Inc. for pavement markings, DRM Associates Inc. for metal deck forms and shear studs, Gull Corporation for flatwork, Hardscapes Construction Inc. for MSE walls, High Steel Structures LLC for structural steel, Interlock Steelworkers for reinforcing steel, Virginia Paving Company for asphalt pavement, Virginia Sign and Lighting Company for ITS/lighting/signals and William B. Hopke Co. for waterline work.

There are approximately 40 construction workers on site on the average day.

In terms of materials installed, there will be nearly 11,000 tons of asphalt, 36,000 sq. ft. of retaining walls, 755,000 lbs. of reinforcing steel and 6,000 cu. yd. of concrete for bridge structures.

CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA