List Your Equipment For Free  /  Seller Login

Vermont's $60M North Hero-Grand Isle Bridge Project Under Way

Thu October 25, 2018 - Northeast Edition #22
Lori Tobias – CEG Correspondent


In addition to the temporary drawbridge the $60 million project includes demolishing the existing drawbridge and replacing it with a new drawbridge.
(EIV Technical Services photo)
In addition to the temporary drawbridge the $60 million project includes demolishing the existing drawbridge and replacing it with a new drawbridge. (EIV Technical Services photo)
In addition to the temporary drawbridge the $60 million project includes demolishing the existing drawbridge and replacing it with a new drawbridge.
(EIV Technical Services photo) Contractors are working to finish a temporary drawbridge linking two islands on Lake Champlain before winter. Work began on the North Hero-Grand Isle Bridge in Vermont this summer. The existing bridge was built in 1953 and is the main road through the islands.

Contractors are working to finish a temporary drawbridge linking two islands on Lake Champlain with a race through the winter to have the new bridge fully functioning in time for the first seasonal opening of the bridge May 15.

Work began on the North Hero-Grand Isle Bridge in Vermont earlier this summer. In addition to the temporary drawbridge the $60 million project includes demolishing the existing drawbridge and replacing it with a new drawbridge.

“They are going to be working on the bridge all through the winter,” said Todd Sumner, senior project manager of the Vermont Agency of Transportation. “They got the temporary out to the abutments and are going to start on the first pier 60 feet off shoreline. The goal is to get all those in, and in the very center of the navigation channel will be one span that opens and closes. After October 15 — when the seasonal openings for boat traffic ended — they will put that span in and then work on electrical and mechanical over the winter so that when May 15 comes around it will be opening by that point.”

The existing bridge was built in 1953 and is the main road through the islands, with 3,000 cars using it daily during the off-season and double that number in the summer and fall months. It also provides the only unrestricted access for boats, and is the only route big sailboats can get through.

The bridge itself is in fine physical condition, Sumner said.

“It's the mechanical and electrical parts of getting it open that is in very dire need,” he said. “The actual capacity to carry traffic is fine. The motors, the electrical, all the mechanics are in really bad shape. The state has been sinking money into it for years just to keep it running. If this project got delayed, there is no guarantee we would be able to open this bridge in the future. There is a risk of not being able to open this bridge.”

Were that to happen, the state could face a $25,000 fine every time it failed to open.

That's why the state can't afford it to happen. That expectation would apply for any bridge.

“The original permit says we are supposed to open on the half hour,” Sumner said. “We've got a one-year deviation to open it once every hour on the hour. That gives us more time for contractors to work between openings, plus if we keep opening it up every half hour all day long, we're worried it is taxing an already overworked old electrical system. We are limiting the chance of operation failure because it is stuck closed or open. It's like owning a house and you bring in new appliances and want to upgrade the wiring, and you realize if you touch that, you are rewiring your whole house.”

Currently, two large cranes are on site, one at each end of the temporary bridge causeway. The cranes will build the temporary bridge from each end, then meet in the middle.

“What happens is they are using the crane to put in the first pier and then put a deck on top connecting the abutment to the first pier,” Sumner said. “Then they drive the crane to the first bent, use the crane to install the next bent and then deck on top of that, connecting first to second and move the crane out. They inch their way across, moving the crane out farther and using it build the next one.”

There also are excavators and trucks on site to complete the infill portion of the project.

The new replacement drawbridge will be located in the same spot as the existing bridge. Otherwise, contractors would have to build a new causeway which would have a permanent impact on Lake Champlain. Building in the same location also saves on the permitting process, which saves money. Likewise, because the temporary bridge has a shorter lifespan, the permitting process also is less involved. The temporary bridge is being constructed on piles, some driven into the rock ledge under the mucky lake bottom. Steel will be used for the bridge foundation with a very thick wood deck placed over the steel.

“This isn't a bridge we're trying to get 100 years out of,” Sumner said. “It's a temporary bridge — the materials won't last that long or handle the ice loading for 100 years. It's designed for a shorter life span and the materials aren't as durable. It only needs to last through construction.”

The completion date is set for the 2022, but the new drawbridge is expected to be substantially complete in the winter of 2021. Contractors will come back in spring of 2022 to make sure new vegetation is thriving, get the field office off the site and demobilize.

CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA