The Commonwealth Transportation Board (CTB) approved two contracts at its monthly meeting on Oct. 24 totaling $414.9 million for maintenance and construction projects in the Virginia Department of Transportation's (VDOT) Hampton Roads and Salem districts.

I-64 Widening, New High Rise Bridge in Chesapeake

A $409.6 million contract was awarded to Granite/Parsons/Corman Joint Venture of Tarrytown, N.Y., to widen about 8 mi. of Interstate 64 and construct a new High Rise Bridge adjacent to the existing span in the Hampton Roads District. The award is the largest design-build contract in VDOT history.

The project will widen I-64 from four to six lanes, beginning half a mile east of the Interstate 264 interchange at Bowers Hill, to one mile east of the Interstate 464 interchange.

The widening will add one high-occupancy toll (HOT) lane in each direction to the existing two general purpose lanes.

The new fixed-span High Rise Bridge will be built just south of the existing High Rise Bridge to carry the three lanes of I-64 west traffic over the Elizabeth River. The existing High Rise Bridge will continue to operate and will carry three lanes of I-64 east traffic upon completion of the project.

The project will include replacement of the overpass bridge at Great Bridge Boulevard and realignment of the associated roadway. The existing bridges carrying I-64 over Military Highway, Yadkin Road and Shell Road will be widened.

The project is being paid for with a combination of funds from the Hampton Roads Transportation Accountability Commission and the state's SMART SCALE program and is expected to be complete in summer 2021. It is designed to accommodate a future Phase 2 project, which will expand the corridor to a total of eight lanes and replace the existing High Rise Bridge.

Two Bridges Will Be Replaced on Route 11

A $5.3 million contract was awarded to Orders Construction Co. Inc. of St. Albans, W.Va., to replace two aging bridges carrying Route 11 (Lee Highway) over Tinker Creek in the Salem District.

One bridge is located near Cloverdale, and the second is located just north of Route 838 (Vista Drive).

The existing bridges were built in 1923 and 1932, respectively. The new structures will be wider and will provide 10-ft. shoulders in both directions. The project is expected to be complete in fall 2019.

Appointed by the governor, the 17-member CTB establishes the administrative policies for Virginia's transportation system. The CTB allocates highway funding to specific projects, locates routes and provides funding for airports, seaports and public transportation.

For more information, visit virginiadot.org and ctb.virginia.gov.




Today's top stories

Protecting Delaware Memorial Bridge

Widespread Catastrophic Damage From Hurricane Awaits Repair Crews in SE States

Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

JCB Celebrates 20 Years of Engine Making

Robert H. Finke & Sons Holds Open House at New Colchester, Vt. Facility

Snyder Civil Leads Way to Provide Clean Water, Safe Communities, More

Today's Security Tech Helps Contractors Combat Jobsite Theft

Komatsu Company Stores East Holds Open House in Pennsylvania


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA