List Your Equipment For Free  /  Seller Login

Walsh Construction Tearing Down, Rebuilding Bridges On I-80

Wed July 14, 2021 - West Edition #15
Irwin Rapoport – CEG Correspondent


Walsh Construction is the general contractor for the $57 million initiative that is demolishing and replacing four concrete structures in Crystal Springs, Baxter, Drum Forebay and Cisco Grove.
Walsh Construction is the general contractor for the $57 million initiative that is demolishing and replacing four concrete structures in Crystal Springs, Baxter, Drum Forebay and Cisco Grove.
Walsh Construction is the general contractor for the $57 million initiative that is demolishing and replacing four concrete structures in Crystal Springs, Baxter, Drum Forebay and Cisco Grove. Bridge superstructures and substructures are in need of major replacement due to the severity of the transverse and longitudinal cracks in the concrete decks, spalling concrete, and high corrosive chloride content in the concrete deck surfaces. Sterling P. Holloway Inc., the demolition subcontractor, employed excavators equipped with hoe rams and buckets to lift the girders and remove the rubble.  Hillside Drilling Inc. based in Richmond, Calif., is drilling the CIDH foundations at Drum and Crystal Springs. Demolition work included the use of two John Deere 250G excavators, a John Deere 350G excavator, a Link-Belt 250X4 excavator, a CAT 950 loader, a CAT 308 mini excavator, a CAT 239 D skid steer., a 60-ft. JLG Manlift, a 2,000 gallon water truck and a 500 gallon water wagon.

As part of the $57.1 million Interstate 80 (I-80) Bridge Rehabilitation Project, Walsh Construction began demolition of the I-80 bridge overcrossing at Cisco Grove. This marked the start of major project construction with completion expected in summer 2023.

The work is part of a project that is replacing four concrete structures in Placer County at Crystal Springs (two lanes, 160-ft. long), Baxter (two lanes, 150-ft. long), Drum Forebay (two lanes, 152-ft. long) and Cisco Grove (two lanes, 293-ft. long), that are being rebuilt with wider overcrossings, 8-ft. shoulders, 6-ft. sidewalks and ramps that comply with Americans with Disabilities Act (ADA) standards.

The new Crystal Springs, Drum and Baxter bridges will be 150-ft. long and 49-ft. wide (two lanes) while the new Cisco Grove bridge will be 293-ft. long and 32-ft. wide (two lanes).

The bridge replacements, built for the highway that led to the 1960 Winter Olympics in Squaw Valley, are due to deficient structural components that were discovered by inspections. According to officials, bridge superstructures and substructures are in need of major replacement due to the severity of the transverse and longitudinal cracks in the concrete decks, spalling concrete and high corrosive chloride content in the concrete deck surfaces

Scope of Construction

Thus far, Walsh crews have completely demolished the Drum and Crystal Springs bridges and the southbound half of the Cisco Grove bridge, with reconstruction ongoing for all three bridges. The demolition operations dealt with Cisco Grove first, followed by Crystal Springs and then Drum.

"Cisco Grove is being demolished in phases," said Dan Hart, Walsh's senior project manager, "and now we're rebuilding one half of the new bridge. After we complete it, I have to move traffic onto it and demolish and rebuild the other side. We're rebuilding the three bridges to provide access back to the community before we could demolish and reconstruct Baxter."

The basic plan of attack for the demolition was to first remove the metal railing and barrier rail on the top and then bring down the rest of the structure, finishing with the columns and footings.

Sterling P. Holloway Inc., the demolition subcontractor, employed excavators equipped with hoe rams and buckets to lift the girders and remove the rubble. Crews used two John Deere 250G excavators, a John Deere 350G excavator, a Link-Belt 250X4 excavator, a Cat 950 loader, a Cat 308 mini excavator, a Cat 239 D skid steer. a 60-ft. JLG manlift, a 2,000 gal. water truck and a 500 gal. water wagon.

"Excavators were equipped with various attachments depending on the task," said David Holloway, Sterling P. Holloway's CAO and estimator. "Some of the major attachments include Rammer hammers of various sizes from 1,000 foot-pounds to 8,000 foot-pounds, Allied Gator shear and various buckets. The skid steer was used for final cleanup and was equipped with bucket and powered sweeper attachments."

"This company has probably demolished 25 bridges along the Highway 80 roads," said Hart. "They have been working with me since the mid-90s and communications between us is fantastic."

Early challenges are being dealt with successfully.

"One of the overall challenges, which is out of our control to a point, is the excavation of the foundations at Cisco Grove and not knowing if it is hard rock," said Hart. "We had an idea that it was hard rock, but did not know how hard it was – that was the risk of the job. We have now excavated all of the granite. I had to bring in rock splitters to get the site to final grade."

Holloway had 10 people on-site for the demolition.

"We were contracted by Walsh for the removal of four bridge overcrossings — Cisco Grove, Baxter, Drum and Crystal Springs," he said. "We completed the first phase, which included the partial demolition of Cisco Grove and the complete demolition of Drum and Crystal Springs overcrossings. We will be coming back later in the year for stage two demolition of Cisco Grove overcrossing, and the complete demolition of Baxter overcrossing. We had a few months to plan and ramp up for the demolition.

"Our crews performed wonderfully," he added. "We have an experienced team that works great together. Each and every one of our team members has put 100 percent into the making sure things go smoothly and safely. We are a family business with three generations of Holloways currently involved with the company, so there is a lot of pride that goes into the work that we do."

Each bridge had a detailed demolition plan and asbestos removal work plan prepared by Del Valle Consulting.

Holloway noted that relations with Walsh and Caltrans have been great.

"It is nice to be on a project where all parties involved work together," he said. "There are always obstacles and challenges in this type of work, and having a leadership group that helps solve problems instead of putting up road blocks makes the project run much more smoothly for everyone."

The company's managed team included David Holloway (project manager), Sterling P. Holloway IV (operator/superintendent), Jake Brower (operator/foreman) and Linda Myers (office manager).

The major wear and tear issues for Holloway were items such as broken hydraulic lines, point wear from the concrete breakers and normal service maintenance such as greasing the machines during every shift and keeping up with other service items for equipment.

"All of our operators have service trucks and carry tools and parts to take care of everyday service and normal wear and tear," said Holloway. "So far on this project, our equipment has not required any major repairs. The keys to good equipment maintenance is preventative maintenance. If you can catch problems while they are small, the big problems can usually be avoided. The last thing you want is to have a key piece of equipment go down with a major mechanical issue while you sitting in the middle of the freeway with a bridge partially demolished and the clock ticking."

Bridge construction, which began in late April, is proceeding on schedule. Work on the Crystal Springs bridge began as soon as demolition ended.

"The Abutment 1 footing is placed and we are ready to pour the concrete for it," said Hart. "We're ready to place Bent 3. I had problems with the rock at Bent 2 and Bent 4, but that has been resolved and we started on those a few days ago. If everything goes well, we should be able to complete the concrete bridges in 2.5 to three months. The footings, columns and caps are poured-in-place. After the girders for the bridge deck are placed, then we'll pour the concrete deck. The bridges are basically precast boxes that fit together and then you stress and traverse to create the superstructure and then you pour the deck."

With the bridges at various stages of construction, Hart is able to transfer crews to various work sites, particularly carpenters and laborers. The Cisco Grove site crew consists primarily of carpenters at this point.

Hillside Drilling Inc. based in Richmond, Calif., is drilling the CIDH foundations at Drum and Crystal Springs.

"We're drilling up to 72-inch foundations that require casings complete with concrete and rebar," said Hart.

For the bridge construction, Walsh is using a John Deere 450K LGP dozer, a Cat 336EL excavator, a Cat 325F excavator, a Cat 420 backhoe, a Volvo L90H loader, a Link-Belt RTC8068 crane and an Xtreme XR 1045 forklift.

The Walsh management team includes Assistant Project Manager Paul Barr; Superintendent Ray Roque from Seattle; Superintendent and Estimator Mark Petty; Field Engineer Jacob Daoust and interns Shawn Elliott from Oregon State and Gerardo De Jesus-Salazar from California State University, Fresno.

"I have crews that I handpicked," said Hart. "It's smaller than I am used to, but I know all of these people and have worked with them over the past 10 years. We a good group dynamic and that is reflective of the progress we have made."

Peak days on the project have 40 plus workers that includes local and regional subcontractors.

The bridge demolitions should generate 5,000 tons of concrete, 300 tons of steel, 5,000 tons of asphalt and 200 tons of earth and rock.

"Recycling is very important to Walsh," said Hart. "The subcontractors are recycling everything they possibly can. It's great for the environment and the pocketbook as the cost of aggregates are expensive."

New materials to be brought in should include 700 tons of steel and 10,000 tons of asphalt and 12,000 tons of concrete.

Hydraulic leaks and punctured tires are among the common wear and tear issues.

"Depending on the severity of the issue, most repairs are usually done in a day," said Hart. "So far we've not seen anything out of the ordinary."

Mechanics from nearby dealerships, such as Holt CAT and United Rentals have been hired to make repairs.

"Most of the equipment that we have on-site is ours," said Hart. "We are based out of Chicago. Some of our equipment in northern California was mobilized to this site, such as an excavator, a crane and a forklift from a work site in Adin."

Sterling P. Holloway purchases and rents equipment from Bejac Corporation, Holt of California and Pape Machinery, all located in Sacramento.

"Dealerships play an important role," said Holloway. "The work we do would not be possible without the right equipment. Working with dealer to ensure that the equipment fits the tasks is where it all starts. Relationships with dealerships happen over time. When people follow through and do what they say they are going to do, strong relationships tend to grow. It all comes down to product quality and service. When purchasing equipment there are more things to consider than the price tag. Being able to get service and parts quickly means everything. Demolition is hard on equipment, so having confidence and trust in the product and the dealer is very important." CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA