List Your Equipment For Free  /  Seller Login

Walsh Makes Progress on ODOT's I-480 Valley View Bridges

Tue March 03, 2020 - Midwest Edition #5
Irwin Rapoport – CEG Correspondent


Solid progress is being made on the multi-year $227 million, design-build I-480 Valley View bridges deck replacement project in northeast Ohio.
(ODOT photo)
Solid progress is being made on the multi-year $227 million, design-build I-480 Valley View bridges deck replacement project in northeast Ohio. (ODOT photo)
Solid progress is being made on the multi-year $227 million, design-build I-480 Valley View bridges deck replacement project in northeast Ohio.
(ODOT photo)
 In August, crews began installing stay-in-place forms in preparation for bridge deck pours.
(ODOT photo) Ironworkers detail the steel in span 5.  
(ODOT photo) Gantry crane system works to set a steel girder across span 5.
(ODOT photo) Iron workers affix the stiffening truss to the lead steel girder with the gantry crane system.
(ODOT photo) Cranes are crucial to the work and a sophisticated system of three interconnected gantry cranes that can be operated by a single operator has been set-up.
(ODOT photo)

Solid progress is being made on the multi-year $227 million, design-build I-480 Valley View bridges deck replacement project in northeast Ohio, an Ohio Department of Transportation initiative that began in November 2017 and will be completed by June 30, 2024.

The initiative — constructionequipmentguide.com/walsh-construction-leads-major-227m-i-480-bridge-work/40176 — also includes the construction of a new east-west bridge between the two existing bridges that will ultimately carry two lanes in each direction.

The contract, awarded to Walsh Construction Company, is re-decking and renovating the twin bridges (in Cuyahoga County, four lanes in each direction) that link Valley View with Independence, which spans the Cuyahoga River, Ohio and Erie Canal, and CSX rail lines, as well as crossing Canal Road, West Canal Road, and the Ohio/Erie Towpath Trail.

The two bridges, constructed in 1975 and opened to traffic two years later, are steel multi-stringer highway girder types that are 212 ft. above the river. The longest span is 300 ft. long. Up to 180,000 cars and trucks cross the bridges daily, and traffic volumes are not expected to change with new bridge construction.

At more than 40 years old, the lifespan of the decks has been maximized and are showing their age.

Crews have been busy working on the new center bridge and according to ODOT, 90 percent of the substructure and 75 percent of girder erection have been completed, with the remainder to be completed by the end of spring. Walsh plans for bridge deck pours, to be complete next summer.

"The new bridge is expected to be used in fall of 2021," said Amanda McFarland, Northeast Ohio Public Information Officer, ODOT Office of Communications. "That's when eastbound traffic on the current bridge will shift to the new one to allow the old eastbound bridge deck to be replaced. That will take about a year to complete. In fall 2021, traffic will be shifted again. The westbound traffic will then use the new bridge while the old westbound bridge deck is replaced. That deck replacement also will take one year. In fall of 2022 traffic will return to its original configuration, as it is today, so that a middle divider can be added to the new bridge to separate traffic."

Last spring saw the start of the steel erection for the new bridge, which led to four lanes on the east and westbound bridges to be shifted to the right to accommodate the many heavy pieces of construction equipment — an arrangement that will remain in place until next fall. The work platform will be placed under the existing bridges, with the first work platform scheduled to go up in 2020 under the eastbound bridge. Concrete barriers on the bridges separate the traffic from equipment and workers.

The job is being done with crews putting in 10 to 12-hour shifts, sometimes six days a week. John Tracy, Walsh's project manager is overseeing the work. He is assisted by Shawn Thompson, CH2M, design project manager, and Tom Bolte, B&N Independent Design quality manager.

Substructure work continues through the winter months into early next year and steel erection is scheduled to begin in late winter.

Work to be completed in 2020 includes: substructure concrete; structural steel erection; catwalks; deck formwork; deck reinforcing steel; deck riding surface; parapets; patching of existing substructure; installation of the platform under existing I-480 eastbound deck; implementation of phase 3 placing of traffic onto the new bridge; and deck removal of the eastbound deck in late fall.

"Weather, especially the wind is one of the biggest issues," said Kirk Gegick, ODOT project engineer. "Wind limitations on crane work down below in building the columns and caps has been a factor, as well as on the gantry cranes and setting the steel. Minor weather delays in 2018 were made up during the 2019 season."

The pile driving has been completed.

"The footing at pier 14, was supposed to be constructed as a spread footing on rock," said Gegick. "We changed it to a pile supported footing, instead of a spread footing on rock when it was discovered that the rock was not found to be at the anticipated elevation. We're sequencing the work to keep work moving during the redesign of this location. It could have been a bigger delay without the partnering of the contractor and ODOT."

Safety measures are a constant on the project.

"Load analyses were completed ahead of placing and using the gantry crane system," said Gegick. "The crane system is very sophisticated and ensures that each load carried across the bridges is distributed within the limitations required by the analysis. ODOT has restricted overweight loads being allowed to cross the bridge during construction of the new bridge.

"Walsh is very proactive at safety," he added. "Examples of this include: the use of leading-edge retractable harnesses, a strategic partnership with OSHA and local unions, the use of flip charts on gantry cranes to clearly list load limitations for steel erection, and real time scheduling of steel deliveries to prevent overweight loads from operating on the bridges while steel erection is ongoing. ODOT is also taking steps to ensure that construction materials can be delivered efficiently.

All superstructure materials will be delivered in the existing mainline median area.

"The area is wide enough to accommodate even the largest girders," said Gegick. "Traffic was shifted across the bridge, and a portable barrier was put in place to create a safe environment for motorists and workers and to accommodate deliveries. "

A shared project management office allows for face-to-face communications throughout the day.

"We have a commitment to a project partnering process and a dispute resolution process is in place for addressing issues," said Gegick. "Maintaining strong partnering will continue to keep this project moving smoothly and on schedule. Lessons learned from the new center bridge superstructure will be applied to the existing bridge deck replacements. High power overhead aerial lines above the bridge created a clearance issue that was addressed. We also ensured that underground electric duct banks next to pier 4 were not disturbed during pier construction."

Cranes are crucial to the work and a sophisticated system of three interconnected gantry cranes that can be operated by a single operator has been set-up. Each crane has been equipped with a laser guidance system to ensure specified distances between them. The bridges support the weight of the cranes, and the cranes travel via a rail track that spans the length of both bridges.

"The proximity of the existing bridges, 2.5 feet between the parapet walls of each bridge, and their height is a challenge," said Gegick. "Setting up the rail system took a couple of months during the winter. The cranes, specially made for the project, took several months to fabricate and be shipped to the project. Once they arrived, it took two weeks to build them and another week to set them up."

Routine physical inspections of the bridges every two weeks during steel erection are done to monitor the condition of the existing bridges.

"The gantry cranes are not only used to erect structural steel, they are also used to support the entire superstructure operation," said Gegick. "Use of the gantry crane system is dependent upon the wind conditions, and work will continue through the winter months, weather dependent. The substructure work began in 2018 and steel erection began last spring when the substructure had progressed far enough to give the steel crews the space they required. Once the girder placement work had progressed enough, work began to ready the bridge for deck pours."

The pour sequence on the new center bridge will be across the Valley from east to west, just as the girders are being set.

"Each individual pour will be approximately 300 feet long and there will be 15 pours on the new center bridge," said Gegick. "The concrete will be delivered on the eastbound bridge work zone for the new bridge. A conveyor is being used to distribute the concrete across the width of the new bridge. The pours will be completed at night from approximately 6 p.m. to 6 a.m."

Due to the scope of the work, other general contractors are following the project and presentations have been given at industry conferences regarding construction of the new bridge.

No work has been done on either of the existing bridges up to this point to prepare them for bridge deck replacement operations. The deck removal operations will begin in late fall/early winter 2020.

"The current plan is to recycle the deck slabs into crushed recycled aggregate," said Gegick. "The reinforcing steel will be sold for scrap and recycled into other steel products. None of the material will be recycled for use on this project."

Some of the major equipment Walsh is using includes a Kobelco 2750 crane; Link-Belt 248 cranes; a Grove 760 telescoping crane; a Liebherr 895 crane; John Deere 750 dozers; Cat 336 excavators; Volvo front end loaders; a Delmag D-46 pile hammer; an ICE I46 pile hammer; a Bidwell BR4800 finishing machine; a Rotec concrete conveyor; JLG lifts; and three Munck custom overhead gantry cranes.

When completed, the bridges will give motorists a smoother drive and a safer one, which includes fencing, parapet walls and most importantly six lanes in each direction.

"The new bridge will be nearly identical to the two existing bridges," said Gegick. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA