List Your Equipment For Free  /  Seller Login

Willard Airport Updates Entrance, Taxiway

Wed November 11, 2020 - Midwest Edition #23
Lori Tobias – CEG Correspondent


Equipment on site includes track excavators, wheel loaders and bulldozers, along with a host of survey equipment.
Equipment on site includes track excavators, wheel loaders and bulldozers, along with a host of survey equipment.
Equipment on site includes track excavators, wheel loaders and bulldozers, along with a host of survey equipment. Three projects are currently under way, including the rehabilitation of the airport entrance road; the installation of new signage and lighting; and a new taxiway.
 Seventy-five 
years after its dedication, 
the University of Illinois — 
Willard Airport is undergoing 
several major updates adding 
up to just shy of $20 million.
 Cross Construction won the contract for the roadway.
 One of the biggest issues with so many projects is securing the funding. The Bidwell runs on a track system and as they pour the concrete with pumper trucks, this piece of equipment screeds it onto the surface of the new taxiway. The Bidwell helps screed the concrete as crews pave.

Seventy-five years after its dedication, the University of Illinois — Willard Airport is undergoing several major updates adding up to just shy of $20 million. The airport is one of only two commercial airports in the country owned and operated by an educational institution.

"It's an exciting phase for us because we are seeing these major projects come up," said Brian Ewalt, assistant director of operations and maintenance. "The airport is trying to maintain the customer focus. You build a facility and maintain it, but eventually you have to update it. We've maintained our facilities, but are at the point where we need to update."

Three projects are currently under way, including the rehabilitation of the airport entrance road; the installation of new signage and lighting; and a new taxiway.

"Our entrance roadway was in dire need of rehabilitation," Ewalt said. "We did constant cold patchings, things like that. We heard a lot of complaints from people entering the airport."

Cross Construction won the contract for the roadway, using its own milling machine to grind up the old asphalt. That material was then conveyored onto subcontractors' dump trucks and dispersed with crushed concrete to create a berm along the perimeter fence line. The berm helps prevent wildlife from tunneling under the fence.

The signage and lighting project are being handled by Champagne Signal and Lighting, using directional boring and trenching machines, as well as locating equipment. That project is being completed in conjunction with the new taxiway, Alpha 5.

"That is a project that was identified as a runway safety action team item," Ewalt said. "It solves a geometry problem. They're taking out a runway that has two taxiways that converge into one and redoing it to have one taxiway. The Federal Aviation Administration, through some of their design guidance, does not like access to a runway from a ramp or apron that does not have a 90 degree turn in it. It mitigates against runway incursion."

A runway incursion is "any occurrence involving the incorrect presence of an aircraft, vehicle or person on the protected area on a surface designated for the landing or takeoff of an aircraft."

Stark Excavating, headquartered in Bloomington, Ill., is rebuilding the taxiway.

Equipment on site includes track excavators, wheel loaders and bulldozers, along with a host of survey equipment and one piece Ewalt describes as "pretty unique."

"It's called a Bidwell," he said. "It's a screeding machine to pour concrete. What it does is help screed the concrete as they pave. It runs on a track system and as they pour the concrete with pumper trucks, this piece of equipment screeds it onto the surface of the new taxiway. It's used a lot in bridge deck replacement. I've been around concrete paving and seen several different machines being used, but I've never seen this piece of equipment used before. It's an older piece that they own and use, but it works very well. It smooths out the concrete making sure it's being poured at uniform depth and also makes sure it comes out smooth. The area they are pouring is 49 feet wide; with concrete at least 18 inches thick."

The concrete is then grooved so that contaminants, such as ice and snow, will melt and drain off instead of pooling and potentially causing hydroplaning.

Two additional projects are on the drawing board. One is the rehabilitation of Runway 422, one of two runways used by commercial carriers. The $13.7 million project, slated for construction in 2021, also will include new lighting, signage and underground wiring.

"It's going to be a substantial project," Ewalt said. "It will be very similar to the roadway project currently under way. It will be milled to a certain level, then they will be coming in with new asphalt in its place. The job has been let at the Illinois Department of Transportation [IDOT] level. IDOT does all our project letting and that plays into our governance structure here."

Also coming up, a new car rental facility, currently in the design phase. The project will be funded by a $3 a day fee charged renters and will allow rental companies to wash, vacuum and conduct maintenance on the vehicles. They currently work from a tent and must leave the property for maintenance.

"That project is being done to aid the business flow of car companies, but we also feel it provides a better customer feel," Ewalt said.

One of the biggest issues with so many projects is securing the funding, but work in an airport comes with numerous unique challenges.

"The challenge for contractors is it's not highway work and it's not residential work. It's an operational airport. A lot of requirements exist with that. Not only in operation, but where you can stage equipment, making sure it is lighted and flagged. There also are security requirements. It's a much different environment to work in than any other construction project." CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Iconic Hotel Being Demolished to Make Way for Baseball Stadium

MD 4 Project to Add Diamond Interchange

Volvo Construction Equipment Showcases New Products at North American Volvo Days

VIDEO: Anniversary of Highway Workers' Memorial Renews Calls for Work Zone Safety

Yanmar Compact Equipment Introduces New Line of Branded Attachments for Compact Track Loaders

Caterpillar Introduces Dynamic Energy Transfer Solution for Battery, Diesel-Electric Mining Equipment

Five Finalists Compete for Grand Prize Makeover in Bobcat Park and Rec Makeover Contest

VIDEO: Students From Washington, Ohio Earn Top Honors in Annual ARTBA Transportation Video Contest


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA