Work to Resume on Road That Leads to N.H. Motor Speedway

Thu April 25, 2019 - Northeast Edition #9
Associated Press


New Hampshire Motor Speedway
New Hampshire Motor Speedway

LOUDON, N.H. (AP) The state Department of Transportation is planning to resume work on a road near the New Hampshire Motor Speedway.

The work, scheduled to resume April 1, is phase one of a two-phased widening of a 3.5-mi. section of Route 106.

Phase One widens a nearly 1-mi. segment from 800 ft. south of Mudgett Hill Road to 1,400 ft. north of the speedway's south entrance. The project also includes drainage and guardrail improvements and construction of three stormwater treatment ponds.

Speed limits will be reduced to 45 mph during work hours. Drivers should expect temporary lane shifts and occasional lane closures.

The $2.63 million project has a completion date of Nov. 22.




Today's top stories

Georgia Is Moving Ahead to Enhance Highway Networks

Iowa DOT's I-35 Project Includes New Bridges

Year in Review: Bobcat's Major Moments of 2024

Hiring, Retaining Construction Employees Starts With Attracting Right Candidates

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Eight I-15 Bridges Open in Idaho, Project Still Ongoing

Equipment Corporation of America Promotes Schell, Sigmund, McNeill

Hy-Brid Lifts Hires New VP of Sales, Marketing to Spearhead North American Sales Team, Bolster Customer Support


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA