WSDOT Selects Kiewit to Tear Down Alaskan Way Viaduct

Tue June 05, 2018 - West Edition #12
WSDOT


The temporary Alaskan Way surface street will move west of the viaduct with two lanes open in each direction along Seattle’s waterfront.
(WSDOT photo)
The temporary Alaskan Way surface street will move west of the viaduct with two lanes open in each direction along Seattle’s waterfront. (WSDOT photo)
The temporary Alaskan Way surface street will move west of the viaduct with two lanes open in each direction along Seattle’s waterfront.
(WSDOT photo) Thomas and John streets will be reconnected over three blocks of a rebuilt Aurora Avenue North.  
(WSDOT photo)

The demolition of Seattle's aging Alaskan Way Viaduct is finally in view.

On May 16, the Washington State Department of Transportation selected Kiewit Infrastructure West Co. to demolish the viaduct, decommission the Battery Street Tunnel and reconnect city surface streets just north of the nearly complete State Route 99 tunnel.

The design-build contract, which requires the contractor provide both design and construction services of the job, is valued at $93.7 million. Kiewit submitted the “apparent best value” bid — a combination of points received for its technical proposal and its price.

“We are excited to be so close to removing the seismically vulnerable viaduct and ushering in a new era on Seattle's waterfront,” said Brian Nielsen, WSDOT's Alaskan Way Viaduct Replacement Program administrator. “It will be challenging to tear down a major highway in the heart of a booming city but we're looking forward to getting it done safely and as quickly as possible.”

Timelines for the work will emerge after the contract is finalized and the contractor receives approval to begin design work. After that point, WSDOT will be able to share more specifics about how demolition and decommissioning will proceed.

What's Ahead This Year
  • Based on the tunnel contractor's current schedule, WSDOT anticipates the new SR 99 tunnel could open as soon as this fall.
  • By then, the temporary Alaskan Way surface street will move west of the viaduct with two lanes open in each direction along Seattle's waterfront.
  • Before the tunnel opens, WSDOT must permanently close the Alaskan Way Viaduct to realign SR 99 and the ramps at the tunnel portals.
  • After the viaduct permanently closes, contractors could begin limited demolition work in late 2018.
  • Future Work
    • The majority of viaduct demolition work will occur in 2019.
    • It will take up to two years to remove equipment and fill in the Battery Street Tunnel. During this time, there will also be utility improve-ments made along Battery Street.
    • Thomas and John streets will be reconnected over three blocks of a rebuilt Aurora Avenue North.




    Today's top stories

    Des Moines Airport Works With Weitz/Turner On Expansion

    ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

    San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

    Year in Review: Bobcat's Major Moments of 2024

    MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

    Iowa DOT's I-35 Project Includes New Bridges

    JM Wood Holds December Auction in Montgomery, Alabama

    DEVELON Set to Exhibit at ARA Show 2025


     







    39.95234 \\ -75.16379 \\ Fort Washington \\ PA