List Your Equipment For Free  /  Seller Login

Decades in the Making: Vital $410M 6/10 Reconstruction Finally Begins

Wed April 08, 2020 - Northeast Edition #8
Lori Tobias – CEG Correspondent


The $410 million 6/10 reconstruction is the largest construction contract put out in the history of the Rhode Island Department of Transportation (RIDOT).
The $410 million 6/10 reconstruction is the largest construction contract put out in the history of the Rhode Island Department of Transportation (RIDOT).
The $410 million 6/10 reconstruction is the largest construction contract put out in the history of the Rhode Island Department of Transportation (RIDOT). The design build team, dubbed 6/10 Constructors, features Barletta Heavy Division, O&G Industries, DW White Construction and 
Aetna Bridge Company. The “missing move” will be remedied by a new connector coming from 10 northbound to 6 westbound, “flying” over the interchange and meeting back with Route 6. The project is scheduled for completion Nov. 20, 2023. “It [bridge] was held up with temporary steel supports underneath for so long that we had to support the supports,” said RIDOT spokesman Charles St. Martin III. The ramps and bridges comprising the interchange, originally built in the 1950s, had fallen into such a state of disrepair over the years, that seven of the nine bridges were rated structurally deficient.

It took a while, but the project on the books for at least three decades is finally under way and moving smoothly.

The $410 million 6/10 reconstruction is the largest construction contract put out in the history of the Rhode Island Department of Transportation (RIDOT). At its heart is a design build project to rebuild the Route 6/10 interchange west of downtown Providence in the neighborhood of Olneyville. The ramps and bridges comprising the interchange, originally built in the 1950s, had fallen into such a state of disrepair over the years, that seven of the nine bridges were rated structurally deficient.

"It was held up with temporary steel supports underneath for so long that we had to support the supports," said RIDOT spokesman Charles St. Martin III. "It's a major connector interchange. When you add all the cars, you're talking about 100,000 vehicles a day using it. The project sat on the drawing board for literally 30 years. We had an administration change and Gov. Gina Raimondo made it a priority and got it off the drawing board."

The design build team, dubbed 6/10 Constructors, features Barletta Heavy Division, O&G Industries, DW White Construction and Aetna Bridge Company.

The interchanges connect the two-to-three lane limited access Route 6 with I-295 to the three- lane Route 10 that connects to Cranston and then up to I-95 in Providence. When the highway was originally built, it didn't include a connection from 10 northbound to 6 westbound, St. Martin said. The only option was to get off the exit before or after and wind your way through city streets.

That "missing move," will be remedied by a new connector coming from 10 northbound to 6 westbound, "flying" over the interchange and meeting back with Route 6.

"That's a pretty large feature of the interchange," St. Martin said. "It's tall, the piers come out of the ground now and people say, ‘Wow, that's really tall.' The other major feature of the project is an elevated viaduct that is being demolished. The highway will be lowered, so you are removing a lot of elevated infrastructure, a lot of visual and physical blocks. The highway is being lowered and the cross streets — Westminster Street and Broadway — are being rebuilt across Route 10. You're going up visually and creating better pedestrian access."

The challenges on the job are many, said project manager Jay McGinn. There are miles of utilities to be moved, including a major gas line, multiple communication and electrical lines, a significant amount of steel and concrete work and one particularly tricky component involving a century old piece of masonry infrastructure.

"On the approach to the flyover we had a criteria for zero settlement over a 100-year-old brick sewer line that runs underneath," said McGinn. "It's an old-fashioned New England sewer. The abutment goes to the bridge. It's about 37 feet high. All that new soil would put too much stress on the brick sewer. RIDOT, the Federal Highway Administration and the contractor, put our heads together to solve this problem. We found a case study out of Philadelphia where this was used over a brick sewer and it worked out very well. The designer investigated it and the contractor looked at what they needed to do and found it was the best solution."

The project calls for the usual heavy equipment associated with new bridges and roadway, but one crane is particularly impressive, McGinn said.

"We just had a meeting today to talk about a big crane we rented. We've been using a 300-ton Liebherr crane, and just spent the past week lifting beams at night up over the highway. Earlier, we brought in a 600-ton crane with a telescoping boom. We will bring that crane back in when we do some other lifts of steel."

The project is scheduled for completion Nov. 20, 2023.

Here are the highlights of the project from RIDOT's overview:

  • The Huntington Viaduct (Route 10 southbound) will be removed and the roadway lowered to approximately the grade of Route 10 northbound and below reconstructed bridges carrying Westminster Street and Broadway'
  • A direct connection to provide the missing move from Route 10 northbound to Route 6 westbound by construction of a flyover ramp, improving regional traffic flow and reducing local traffic congestion in Olneyville;
  • Replace the Tobey Street on-ramp with a new two-way connection between Tobey Street and Harris Avenue that will enhance access across the highway at this location. A new Harris Avenue connection to either Route 6 westbound or Route 10 southbound (including a new one way westerly service road) will address traffic weaving issues at the existing on-ramp;
  • Construct new bridge crossings over the highway for Westminster Street, Broadway and Harris Avenue/Tobey Street. The roadways will be wider boulevards that will include new, multi-use paths providing separate, safe routes for pedestrians and bicyclists. These new crossings combined with replacing the existing Huntington Viaduct with a depressed roadway will substantially reduce the existing highway barrier to connectivity between the neighborhoods of Olneyville to the west and Federal Hill and West End to the east;
  • New bicycle/pedestrian paths extending through the project area from Union Street to Tobey Street that will enhance connectivity between area neighborhoods and provide a substantial portion of a connection between the Woonasquatucket River Bikeway and Washington Secondary Bike Path;
  • Better local traffic circulation and improved access; and
  • Gateway aesthetics: Additional measures will be taken for landscaping and visual improvements. CEG

Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Protecting Delaware Memorial Bridge

Widespread Catastrophic Damage From Hurricane Awaits Repair Crews in SE States

Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

JCB Celebrates 20 Years of Engine Making

Robert H. Finke & Sons Holds Open House at New Colchester, Vt. Facility

Snyder Civil Leads Way to Provide Clean Water, Safe Communities, More

Today's Security Tech Helps Contractors Combat Jobsite Theft

Komatsu Company Stores East Holds Open House in Pennsylvania


 







39.95234 \\ -75.16379 \\ Fort Washington \\ PA