List Your Equipment For Free  /  Seller Login

Harbor Bridge Project


Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

With work now in its final phase, the countdown is on for completing one of Corpus Christi's most anticipated construction projects. After years of research, public input and collaboration, the new U.S....


Harbor Bridge Project Pushing for 2025 Finish

The Flatiron/Dragados LLC (FDLLC) joint-venture constructing the Texas Department of Transportation's (TxDOT) design-build, $1.2 billion U.S. 181 Harbor Bridge Project (HBP) in Corpus Christi is pressing forward and making considerable strides for an initiative that not only improves traffic flow and enhances commercial activity, but is improving life for area residents....


TxDOT, Contractor Agree to Resume Harbor Bridge Project

The Texas Department of Transportation (TxDOT) has reached an agreement with the developer of the New Harbor Bridge Project, Flatiron/Dragados LLC (FDLLC), that settles all outstanding disputes and damage claims....


TxDOT, Contractor Take Steps to Resume Harbor Bridge

TxDOT and Flatiron Dragados LLC (FDLLC) have executed a signed letter agreement that establishes the legal framework for resolving the safety issues identified in the design of the New Harbor Bridge Project....


Contractor, TxDOT Work to Continue Harbor Project

TxDOT has recently had productive communications with Flatiron Dragados LLC (FDLLC) and its parent company, ACS Group, regarding concerns over the construction on the Texas Harbor Bridge project. Those discussions have taken a new direction and tone since TxDOT issued a notice of default on Aug....


Harbor Bridge Project Crews Have Productive Summer

The summer months were an incredibly productive time for construction progress around the South Interchange or future tie-in point for IH 37, SH 286 (Crosstown Expressway) and US 181. Despite initial rain delays, roadworks and structure crews met several goals to accomplish major upcoming traffic shifts, connector switches and demolition of existing ramps around the IH 37 and SH 286 Interchange....


CCHB Crew Pours Concrete

Over the past month, crews on the south side of the Harbor Bridge project in Corpus Christi achieved a major milestone with the completion of the largest concrete pour to-date on the project. The pour was part of the construction of the footing for the south pylon and included 3,100 cu....


First Pre-Cast Segment Reaches Corpus Christi Harbor Bridge Work Site

On Sept. 4, the Corpus Christi Harbor Bridge project reached a major milestone when the first pre-cast segment was delivered to its North Approach. The segment weighs 135 tons and is the first of about 2,600....


Harbor Bridge Crews Achieve Project Milestone

Harbor Bridge Project (HBP) crews have reached another milestone with the completion of 40 drilled shafts on both the north and south side of the project. The 40 drilled shafts will make up the foundations of the two bridge pylons....


HBP Crews Provide Recovery Assistance in Wake of Storm

Heavy equipment operators, superintendents, field crew members, subcontractors and employees from all different backgrounds and specialties joined forces to assist with clean-up efforts for those hardest hit by Hurricane Harvey....


Today's Top Stories

  1. Turner Construction Leads $675M Concourse Project  →
  2. Boston, MBTA Officials Reveal New Designs for Future Blue Hill Avenue Transit Project  →
  3. Balfour Beatty Begins $95.5M Mixed-Use Project in Dallas  →
  4. Clark Construction Breaks Ground On Forensic Hospital  →
  5. Exact Crane & Equipment Now Carries Jekko Product Line  →
  6. MDOT SHA Holds Annual 'Snow Show' in Hagerstown  →
  7. New Data Center Planned for Fayette County, Ga., Could Be World's Largest  →
  8. VIDEO: Vermeer Unveils D24 Horizontal Directional Drill, Marking New Era in Utility Installation  →
  9. Construction Has Begun On Innovative Proton Therapy Cancer Center in Connecticut  →
  10. Ohio Forestry Association Holds 66th Annual Paul Bunyan Show  →
  11. Two Monster Machines — The ACCO Super Dozer, Motor Grader  →
  12. CPI Lands Lone Star Paving in Austin for $654M, 3M Shares  →
  13. Depreciation Bonus Begins Phase-Out  →
  14. Brandt Adds McCoy Construction to U.S. Material Handler Dealer Network  →
  15. Innovative Startups to Share Vision of Future of Construction, Mining at Hitachi Construction Machinery Challenge  →
  16. CEG Speaks With New President of Chadwick-BaRoss, Thompson Equipment  →
  17. Stillwater Regional Airport Starts Work On $27M Terminal  →
  18. Webber LLC Nears End of I-35 at SH 123 Project in Texas  →
  19. Work Is Under Way to Develop 84-Mi-Long Mountain Bike Trail in Rural Maine County  →
  20. California's I-80 Pavement Rehab Project Moving Along  →
  21. Raising I-95 in North Carolina's Coastal Plain  →





39.95234 \\ -75.16379 \\ Fort Washington \\ PA